Portfolio

According to the Standard for Portfolio management, “a portfolio is a collection of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.” A portfolio exists to achieve organization and business unit strategies and goals and may consist of current and future components.

The aim of creating portfolios is to use the synergies between the activities to increase efficiencies:

portfolio.png

Portfolio Management

Portfolio management is the centralized process of managing one or more portfolios to achieve strategic objectives. It involved the following steps:

  1. Identify projects, programs, and non-project activities
  2. Categorize the activities: Locate project at the right place (program, portfolio) for better coordination
  3. Evaluate and prioritize items in a portfolio
    • Limit no. projects for focus and fit
    • Identify co-dependent projects
    • Eliminate high risk low return items
    • Eliminate items that skip the formal selection process
  4. Balance the portfolio
    • Prevent overloading the organization
    • To balance the resources with needs
    • To balance returns
    • To balance short-, medium-, and long-term returns
  5. Authorize projects

In essence:

Portfolio management:

The core principles in the Standard for Portfolio management are:

Portfolio Management Life-cycle

Portfolios (like projects) go through a series of life phases:

  1. Initiation: Through strategic planning, organizational objectives and goals are defined, and a long-term roadmap is developed for the organization.
  2. Planning: A management plan is created to manage budget, identify interdependencies and risks, resourcing and prioritization and confirmation of governance body and performance metrics
  3. Execution: The portfolio components are delivered and reprioritized as required.
  4. Optimization: Make the portfolio as effective as possible by maximizing available conditions, constraints and resources. Throughout this life cycle, monitoring and controlling is used to monitor benefits realization and portfolio resource utilization, and take actions to correct performance.

portfolio-life-cycle.png

This table provides an example of some of the major activities duringthe portfolio life cycle.

Level Stage Major Activities
Portfolio Level Initiation (Each Portfolio) - Portfolio strategy and management plans created
- Portfolio management process (vision, governance, and stakeholders)
- Governance and communication planning defined
- Ideation process defined
- Portfolio selection and prioritization criteria defined
- Portfolio charter defined
- Value metrics defined (financial and nonfinancial)
- Portfolio roadmap
Portfolio Level Planning - Yearly goals/objectives set
- Revisit governance structure
- Capacity and capability planning
- Portfolio strategic alignment updated
- Portfolio metrics refined
- Optimization/transition of portfolio
- Portfolio roadmap refined
- Adaptive—portfolio continuously realigned to strategy-based changes to strategy, business, and technology factors
- Time frame—yearly and recurring
- Portfolio plans revised
Portfolio Level Execution - Optimization/transition of portfolio
- Portfolio health reported—status and metrics
- Demand and resource capacity planning adjustments
- Governance decisions via change management (portfolio)
- Adaptive—portfolio continuously realigned to strategy-based changes to strategy, business, and technology factors
Portfolio Level Optimization - Reoptimization of portfolio
- Lessons learned (portfolio level)
- Portfolio closed
- Demand and resource capacity planning adjustments
- Governance documents revisited
- Value metrics revisited
- Adaptive—portfolio realigned to strategy based on adjusted business factors
Component Level Initiation (Each Portfolio) - Initial component lists created
- Component lists reviewed based on alignment to strategy and prioritization criteria
- Component list validation feedback incorporated into revised planning
Component Level Planning - Feasibility reviews and POCs
- Portfolio component list reviews (iterative) and finalization
- New programs/projects solicited via ideation process
- Review new components and authorize
- Adaptive—portfolio components updated based on changes to customer values, strategy, products, and services
Component Level Execution - Governance decisions via change management (components)
- New programs/projects solicited via ideation process
- Review new components/authorize
- Feasibility reviews and proof of concepts
- Pilots launched in support of proof of concepts
- Governance decisions via change management (component)
- Exception-based components authorized
Component Level Optimization - Revisit business cases for adjustments
- Output of pilot component successes and proof of concepts
- Portfolio components closed
- Lessons learned (component level)
- Benefits accountability defined (migrate to operations)
- Artifacts archived for components

Creating a Portfolio

Similar to projects, portfolios also need to be initiated. Usually a portfolio charter is set in place, which formally authorizes the portfolio manager to use resources towards the goals of the portfolio.

This document is developed based on the strategic plans of the organization, its process assets and enterprise environmental factors and will includes information on:

Portfolio Governance

Portfolios should be governed to ensure transparency, responsibility, accountability, fairness and sustainability. The approach to governance needs to take into account the legislative and regulatory environment, and decision-making hierarchy of the company. It should be aligned with how the organization governs its other activities, and its culture.

Example

  1. A college creates a “Digital Transformation Portfolio” including:
    • Online registration system.
    • Learning analytics initiative.
    • Finance and HR system upgrades. Portfolio KPIs might include:
    • % of portfolio budget allocated to student‑facing projects.
    • Aggregate NPV of approved digital projects.
    • % of projects on track for benefits realization and strategic objectives.
    • Resource utilization across critical skill sets (e.g., integration specialists).
  2. A city’s infrastructure portfolio includes:
    • Multiple bike lane corridors.
    • Road resurfacing projects.
    • Bridge maintenance and replacement projects. Portfolio management:
    • Categorizes projects by strategic goal (safety, climate, mobility).
    • Balances short‑term “bread‑and‑butter” maintenance with long‑term transformative projects.
    • Uses governance processes to prioritize and sometimes stop projects that no longer support strategy.

Portfolio Capacity and Capability Management

An important element of portfolio management is maximizing resource utilization. This is done through capacity and capability management:

There are 4 major categories of resources to consider:

Elements of capacity management include:

Capability Management

Capability Management elaborates what aspects of resource capacity are available and addresses the attributes, competences, and skills associated with resources and organization support for portfolios. Capability Management involved:

Challenges with developing capability may include:

Balancing Capacity and Capability

There is a direct link between capacity and capability. Say, if your company has a capability owing to the talent it has, then the number of people with that expertise becomes an important capacity factor. This limited capacity can impact how many projects or programs using this capability can be undertaken by your organization.

Summary