Cost Management

Learning Objectives

By the end of this unit, you should be able to:

Cost Management Processes

In this section, we will review the planning process group elements that have to do with cost. These processes are used to create the initial cost estimates and plan, and to update this information as the project progresses.

Plan Cost Management

The goal of this process is to create the cost management plan, a description of how you will be managing costs. Some of the information here include the accuracy of the estimates, the estimation methods used, and the categories of costs.

The process has the following elements:

Estimate Costs

The goal of this process is to estimate the cost of each work package. The process has the following elements:

Determine Budget

The goal of this process is to estimate the total cost of the project. The process has the following elements:

The Budget

Budgeting is forecasting:

Creating the budget involves 3 elements:

budget-components.png

A study of 258 projects in 20 countries showed that nine out of ten projects experience cost overruns, and sometimes by over 100 percent! According to one expert in project management, due to natural optimism at project start, most PMs underestimate their projects’ costs by 30 percent or more

Budgeting Considerations

Categorizing Costs

By this time in your studies, you may be familiar with different approaches to classifying costs:

While all these elements are important, project management cost estimation mainly focuses on identifying direct costs, and from there any additional charges that are indirect.

Direct Costs

At work package level, cost estimates focus on direct costs related to work defined in the scope. Direct costs are directly attributable to the project work (a specific cost center or cost object such as a department, process, or product). They directly go into producing goods or providing services. In most cases these costs are based on a per hour or per unit rate.

Some examples of direct costs for a work package include:

To determine the cost of each workpackage:

Some organizations may use forms like this to capture the resource needs of each work package:

Resources   Person to Contact How Many/Much Needed When Needed Check (✓) If Available
People          
  Managers, supervisors        
  Professional & Technical        
  Nontechnical        
Money          
Materials          
  Facilities        
  Equipment        
  Tools        
  Power        
  Space        
Special Services          
  Research & Test        
  Typing/clerical        
  Reproduction        
Others          

Indirect Costs

Indirect costs are general business expenses needed to keep you operating. They can include:

Contingencies and Reserves

During the project, mistakes may be made: you may order the wrong part, make an error in your calculation. Moreover, there are risk events that may take effect, some of these you may be able to predict and prevent (a worker may be injured during an activity), while others are hard to predict (a global pandemic).

Your budget must include adequate money to navigate such issues. There are two types of reserves set aside for projects:

Reserves are usually estimated as a percentage of the total cost. They can be calculated more accurately using Mote Carlo and other probabilistic methods for contingency reserves, based on the firmness of the scope description, and therefore the riskiness of the estimates.

There are several different ways to include contingencies in your costs and budget:

Aspect Contingency Reserve Management Reserve
Purpose Covers known unknowns — identified risks in the risk register Covers unknown unknowns — unforeseen scope or events
Location in Budget Inside the project budget / cost baseline Above the project budget / outside the baseline
Who Controls It Project Manager Sponsor / Client / Change-Control Board
How It’s Used Drawn down as risks materialize; no formal change request needed Released only through formal change control
Sizing Method Quantitative risk analysis (e.g., EMV, Monte Carlo) Sponsor policy (often % of total budget)
Visibility in EVMS Included in performance measurement baseline Not included in baseline; not visible in EV calculations

Cash Flow

In most contracts, funds are released incrementally. As a result, the organization needs to know when funds are made available, and when they are used by the project. This is usually done by using the project schedule to map costs on a timeline, creating a cash flow chart for the project. Your project burn rate is then the amount of money you use in a specific period ($ per month).

Task Estimate ($) January February March April May June July August
A 7,000 5,600 1,400            
B 9,000   3,857 5,143          
C 10,000   3,750 5,000 1,250        
D 6,000   3,600 2,400          
E 12,000       4,800 4,800 2,400    
F 3,000         3,000      
G 9,000     2,571 5,143 1,286      
H 5,000         3,750 1,250    
I 8,000           2,667 5,333  
J 6,000               6,000
Total 75,000 5,600 12,607 15,114 14,193 9,836 6,317 5,333 6,000

Example: Vallye College Online Registration

Sample Work package: “Develop web frontend” (for the Valley College Online Registration System).

Resource Costs:

Direct costs: CAD 13,400.

Direct project overhead (e.g., workspace utilities) might be estimated at 10% of direct labour as per company policy → ≈ CAD 1,240.  

General and administrative overhead could be 15% of total direct costs as per company policy → ≈ CAD 2,010.  

Total estimated cost for this work package ≈ CAD 16,650.

We may do this calculation for all workpackages. Perhaps we end up with:

Total assigned funding = CAD 300,000.

Our planned cash flow may look like this:

Average burn rate ≈ CAD 31,250/month, with a peak of CAD 40,000/month during build and integration. Monitoring actual cash flow against this plan helps detect early cost overruns.

Cumulative Cost

From a cumulative cost perspective, projects follow two patterns:

Presenting the Budget: Activity/Category Versus Program Budgeting

Most organizations use an accounting system with specific cost categories to keep track of their expenses. This cost categorization is usually activity oriented: Expenses are assigned to standard budget lines (labour, travel, etc) and these liners are aggregated and reported by each organizational unit. Management is used to seeing budget information broken down this way.

However, project and program budgets are focused on specific work package activities and time periods for aggregation across the project. In fact, different projects may use different categories to report costs.

While project managers estimate and use costs using the latter method, they need to report information using the former approach for ease of understanding by management.

3998c0aee67d3a855a7c300294ddf691.png Creating an Accurate Project Budget: Step-by-step Guide for Project Managers (itpmschool.com)

Creating the Budget

Summary