By the end of this unit, you should be able to:
Estimating is the process of forecasting or approximating. In planning a project, we need to estimate various parameters including the duration of activities, the effort needed for activities, the costs of activities, contingency reserves, and impact of risk. This information in turn will form the basis to finalize the plan including schedule the work, create a budget and cash flow information. This plan is what is used to monitor the progress of the project and make decisions. Hence, estimating is a key skill for a project manager.
When working with estimates, we need to know:
Estimates are updated throughout the life of the project at specific points to increase accuracy of future estimates. One should avoid gold-plating here: your estimate should truly be what you expect to happen, and your aim during execution is to meet the estimate.
There are two general approaches to estimate information in the project
| Top-Down Estimates | Bottom-Up Estimates | |
|---|---|---|
| Intended Use | Strategic decision making | Detailed planning |
| Feasibility/conceptual phase | Detailed budgeting | |
| Rough time/cost estimate | Detailed scheduling | |
| Funding requirements | Resource requirements | |
| Resource capacity planning | Timing of funds | |
| Internal/small project | Customer wants details | |
| Unstable scope or high uncertainty | Well-defined scope with time and cost as main constraints | |
| Preparation Cost | 0.1-0.3% of total project cost | 0.3-1% of total project cost |
| Accuracy | -20% to +60% | -10% to +30% |
Top-down and bottom-up estimates may be used together. Say you are completing a project with 5 phases. You may do a top-down estimate for the phases (allocating specific amounts of the budget to each phase), and a bottom-up estimate for the phase you are immediately working on (to ensure the project is feasible and identify where the expenses are).
Near the end of the current phase, you may update the top-down estimates for future phases, and perform a bottom-up estimate for the next immediate phase. This hybrid approach means you always have the big picture in mind, and detailed information for the immediate next phase, a rolling wave approach to planning.
This approach can be useful for bottom-up approach (to estimate cost of components or specific tasks) or top down. The aim is to rely your estimate on historical/statistical information. This can be information about the cost of parts, equipment or material you can find online. You can also look at how much people have charged for a specific task, the wages for human resources, the amount of time a task has taken in the past and similar information.
Sources of this information can be:
There are several methods you can use which all rely on similarity to other projects. These methods always involve some extrapolation, but can be used to find areas for improvement.
While the project manager can estimate information, consulting the people who will actually do the work and those with experience completing the work will lead to better estimates. Ideally ask the owner of the work package or task for an estimate or involve those with expertise in the specific task or work package. Sometimes this means going outside your organization to get specialized advice, or talking to potential vendors (one reason to develop a good relationship with them on one project is that they will be willing to help you on your estimate for the next project).
Human performance usually improves when a task is repeated. This happens by a fixed percentage (the learning rate) each time the production doubles until it plateaus. This can be calculated as
\[T_n = T_1 n^r\]where T_n is the time it takes to complete the nth repetition, T_1 is the time for the first unit, n is the number of units, and
\[r=\frac{log(rate)}{log2}\]The total time needed to complete the n repetitions is:
\[T_{tot} = T_1 \sum_{n=1}^{N} n^r\]The idea behind the delphi technique is to use multiple estimates from a panel of experts, and moving those experts towards consensus.
Ideally you want to do this in a meeting of peers, with experts in the same task, in the form of a group activity.
The methods we saw to this point rely on developing an absolute estimate, a single number. Nothing is that deterministic in the real world; they are probabilistic with a range of possible results.
To take into account uncertainty of the prediction using a probability distribution, we can instead develop 3 estimates:
If the most likely estimate is the average of the optimistic and pessimistic estimate, then you can use the most likely value directly. Otherwise, we can use the value calculated from a probability distribution (or a weighted average). There are various versions of this, but the most common is using the beta distribution, where the estimate (E) can be calculated as:
\[E = \frac{O+4M+P}{6}\]Now we can also calculate the standard deviation, which tells us how spread out the estimates are and gives us a sense of uncertainty:
\[\sigma = \frac{P - O}{6}\]There is close to 68% likelihood you end up completing the project within the standard deviation.
Example: A Three-Point Estimating Technique: PERT - Project Management Academy Resources
Let’s look at a few examples of estimates during the new Online Registration System project for Valley College.
The team may define an activity for the project as “Configure registration rules.” Within the team, we ask those working on this task for an optimistive, pessimistic and most-likely duration for completing the work:
When planning, we use the expected duration: \(E = \frac{O + 4M + P}{6} = \frac{3 + 20 + 9}{6} \approx 5.3 \text{ days}\) \(\sigma = \frac{P - O}{6}=\frac{9 - 3}{6} = 1\)
This three‑point estimating incorporates uncertainty into duration estimates. If we had not used it, we would have assigned only 5 days for this task. Now we know that the project is 68% likely to complete in 4-6 days (within one standard deviation), and 99% likely to complete in 2-9 days (within 3 standard deviations).
The college identifies that it needs a $2,000 sqft plot of land for a data center to support the project. To estimate the cost to buy this land, they may use the cost per square foot:
\[Cost = \$150 /sqft × 2,000 sqft = \$300,000\]Let’s assume that data center is structures as a separate five‑phase project (concept, design, build, test, deploy). The college may decide to use top‑down estimates for overall phase budgets and durations. Then bottom‑up estimates are used for the current phase to ensure feasibility and identify detailed resource needs. After each phase is complete, phase‑level estimates are updated for future phases as more information becomes available (rolling‑wave approach).
Regardless of method, accuracy will depend on factors including:
High-level estimates (at project level) may be up to 300% off, but estimates of specific work packages tend to be within 15% of the actuals in many cases. The project team needs to determine what their accuracy standards are. One example of a standard could be:
Before one ends estimation, there are two key questions to answer:
Based on your answers to these questions, you may decide to adjust your estimates:
The Association for the Advancement of Cost Engineering (AACE) defines the following class of estimates which are commonly adopted by many organizations.
Source: W4_bud_Selection of cost estimation method for subsea facility in offshore development | TOPAZ SMART
You may decide to adjust your estimates if:
The following sources were also consulted in creating this resource: