Create a milestone chart to summarize the high-level schedule of the project
Understand the linkage between WBS and the project network
Create a network diagram to analyze the sequence of events needed to complete your project using activity on node methods
Calculate early, late, and slack activity times
Identify and understand the importance of managing the critical path
Distinguish free slack from total slack
Demonstrate understanding and application of lags in compressing projects or constraining the start or finish of an activity
Create a Gannt Chart to represent the schedule of the project
What is the Project Schedule?
The project schedule is an operating timetable for the project. It includes information about:
The project activities
The sequence of activities
The duration planned for each activity
Relationships or dependencies between the beginnings and ends of different activities
The project schedule is created after the creation of the WBS and before resource planning: the WBS fully describes the activities that are needed, while the durations selected will link to the resources assigned to the project.
Schedule Creation Processes
In this section, we will summarize the schedule creation processes as described by PMI. Other than Plan Schedule Management, the rest of these processes may be revisited during implementation to adjust the project plan based on changes during the project.
Plan Schedule Management Process
In plan schedule management, the team determines their approach to project scheduling: What form of documentation is used, what assumptions are made and what specific language is used in the project. The process has the following elements:
Inputs
Project charter
Project management plan (Scope management plan, Development approach)
Enterprise environmental factors
Organizational process assets
Tools and Techniques
Expert judgment
Data analysis (Alternatives analysis)
Meetings
Outputs
Schedule management plan
One of the most important parts of planning schedule management, is deciding on the hierarchy of schedules used by the project. Most projects have a hierarchy of schedules that may include:
Program master schedule: a comprehensive high-level timeline of program workpackages, milestones and dependencies of the program. IF a project is part of a program, its schedule has to abide by this timeline.
Project master schedule: a comprehensive high-level timeline of tasks, milestones and dependencies of the project. This usually includes project phases and major milestones, with 10-15 high-level work packages presented. It is usually developed manually and early in the project, and is updated as details become available.
Detailed production/activity schedules: These are usually more detailed schedules for specific activities. They are created by people to whom a workpackage or activity is assigned to.
Control schedules: These schedules are used for tracking progress compared to the baseline planned schedule.
As an example, a development of a housing complex with 4 blocks may be considered a program. The program master schedule tells us when each block has to be completed. Each block will then have a project master schedule which tells us when the structure is complete, when sprinklers are installed, etc. The fire safety company which installed the sprinklers when then take that information and created an activity schedule to install the sprinklers. Both the sprinkler company, and the block developer will have their own control schedules to track how they are progressing.
Tools used to communicate the schedule include:
Go-no go dates: Commonly determined ad hoc (“seat of the pants”) for project control
Task Lists: Useful for really small unrelated tasks
Milestone Charts: Milestones are events (changes in state) in the life of the project, and hence do not have duration or resources. The highlight important points in the life of the project (completion of major tasks, deliverables, etc) sequentially. They can help with communicating high level activities, providing high level control and motivating the team (effort distribution and reduction of stress and panic at the end). A Milestone chart is a timeline showing the milestones of the project. It helps communicate high level schedules.
Logic networks: Show the sequence of activities, and form the basis for determining the start and end dates of activities. They are useful for creating detailed schedules.
Manual bar (“Gantt”) charts: A representation of the schedule from operations management that shows the duration of each activity as a bar. They are useful for communicating detailed schedules.
An activity is an element of the project that requires time but may not require resources. The activity definition process is a further breakdown of the work package elements of the work breakdown structures (WBS). It documents the specific activities needed to fulfill the deliverables detailed in the WBS. These activities are not the deliverables themselves but the individual units of work that must be completed to fulfill the deliverables.
Activity definition uses everything we already know about the project to divide the work into activities that can be estimated. This process includes the following elements:
Inputs
Project management plan (Schedule management plan, Scope baseline, Cost baseline)
Enterprise environmental factors
Organizational process assets
Tools and Techniques
Expert judgment
Decomposition
Rolling wave planning
Meetings
Outputs
Activity list
Activity attributes
Milestone list
Change requests
Project management plan updates (Schedule baseline, Cost baseline)
For example, in a construction project you may have a workpackage which is focused on painting. The paint job can be broken down in different ways. Let’s say we break it down by floor (creating another level in the WBS). Now for completing painting in each floor, there are particular activities that need to happen: area has to be cleaned, primer needs to be applied, paint needs to be applied, etc. These are the activities.
You can see that these activities can be overlapped: you do not need to finish applying primer to all of the floor before you start painting. You could paint an area where primer is applied, while continuing to apply primer elsewhere. That is the whole idea behind this process. By identifying activities at a lower level of detail than the work package, you could see if the work can be done in different ways to make up for time, or money. Of course, if you have a contractor doing this, you as the project manager may just plan the work packages, and have your subcontractor plan the details.
Sequence Activities Process
After the activities are determines, we can sequence them. The aim is to identify how the tasks are related to each other (would one need to be completed after the other one). We also want to identify unrelated tasks which can be completed concurrently.
The process has the following elements:
Inputs
Project management plan (Schedule management plan, Scope baseline)
After determining the sequence of activities, we need to estimated how long the activity will take. It is important to distinguish between the duration of a task and the effort:
Effort is the amount of active time someone needs to spend on an activity. Say if you are booking a flight for another person, this will include the time it takes to search for flights, choose the flight, write them an email so they can confirm that it works for them, and book the flight. It does not take into account the time you have to wait for the person to respond to you.
Duration is the calendar time it takes to complete the task. Let’s assume in the example above you estimates 1-2 hour of effort to book the flight for someone else. Because you have to wait for their response, and you may have to do a back and forth, the duration for this activity might be 2 calendar days, although you will only spend an hour or two during those two days to complete this task.
These two concepts are interrelated, and also related to resources: effort determines how many resources you need and how much you have to pay for an activity. Depending on the task, you may be able to shorten the duration by assigning more than one person to work on it.
Activity durations process has the following elements:
Inputs
Project management plan (Schedule management plan, Scope baseline)
In the next sections we see how this happens in action.
Logic Networks and Scheduling
The basis of project scheduling are logic networks and precedence diagramming method (PDM). These networks depict the activities and their relationship to each other. There are approaches to precedence diagrams: Activity on Arrow (AOA) and Activity on Node (AON). We will focus on the latter. Network diagram are more technical than other tools such as Gannt charts, and help project managers create a plan. They are not a scaled timeline, which is what most people expect out of a schedule.
Scheduling methods were developed around 1950s. Dupont developed the critical path method (CPM), a method which uses precedence diagrams and deterministic (fixed) time estimates to calculate the start and end dates of each activity. Around the same time, the Program Evaluation and Review Technique (PERT) was developed for the Polaris missile/submarine project which uses probabilistic estimates (a probability distribution) for time estimates. Nowadays, project management software have blended the two approaches.
Creating the Logic Network
The precedence diagram/project network is a graphic flow chart depicting the project activities that must be completed, their logical sequences, the interdependencies of the activities to be completed, and the times for the activities to start and finish along with the longest path(s) through the network—the critical path.
For the simple case of two activities, we start with the activities at the nodes and connect them with an arrow, which depicts the relationship between the two tasks.
The first activity is the predecessor and the one at the end of the arrow is the dependent activity or successor.
The relationship between the two activities is also called their dependency, and is determined based on the nature of the activities and context of the project. Generally speaking, the dependency may be:
External: An external entity requires this relationship. For example, you may need to wait for approvals from a regulator before you can move to the next phase.
Discretionary/preference: This is “soft” logic: You prefer this relationship between the tasks but it is not necessary.
Mandatory: This is “hard” logic: It has to be done this way. For example, you cannot sign the contract before your lawyer reviews it.
Distinguishing these helps you when trying to match the schedule to what stakeholders may want. For example, if you complete scheduling and see that the project will not be complete by the time the sponsor wants, you may be able to compress it by adjusting some of those preference dependencies, while external dependencies may require negotiation to be adjusted.
The relationships/dependencies themselves are:
FS (Finish-Start): The predecessor has to finish for the successor to start.
FF (Finish-Finish): The predecessor has to finish for the successor to Finish. When A finishes, B may finish.
SS (Start-Start): The predecessor has to start for the successor to start. When A starts, B may start.
SF (Start-Finish): The predecessor has to start for the successor to finish. Imagine you’re setting up a new software system. One task is “Deactivate the old system,” and another is “Activate the new system.” You can’t finish deactivating the old system until the new system is started. Once the new system is live, you can then finalize the shutdown of the old one.
By default we assume that the relationship is FS. Any other relationship is explicitly written on the arrow. The goal is not to have too many none-FS relationships, unless it is not possible.
In addition to the dependencies, there might be time delays involved in the network:
Lag: A directed delay between activities:One task must wait in relation to another task. This is shown as a positive number with the relationship: FS+4
Example: In commercial construction, a team may pour a concrete foundation (Activity A) and subsequently frame the steel structure (Activity B). The relationship is Finish-to-Start (FS). However, the concrete requires a mandatory seven-day curing period. The project manager applies an FS relationship with a seven-day lag, meaning Activity B cannot commence until seven days after the completion of Activity A.
Lead: The acceleration of a successor activity: The task must start before the predecessor is done. This is shown as a negative number with the relationship: FS-4
Example: Consider a massive landscaping project for a corporate campus. The team must lay sod (Activity A) before planting decorative shrubs (Activity B). The relationship is naturally Finish-to-Start. However, because the campus is expansive, the team does not need to wait for the entire property to be sodded before planting shrubs in the completed sectors. The project manager applies a three-day lead (often calculated in scheduling software as a negative lag). Therefore, Activity B can commence three days prior to the total completion of Activity A, effectively compressing the schedule.
Some basic rules for creating project networks:
1. Networks flow typically from left to right.
2. An activity cannot begin until all preceding connected activities have been completed.
3. Arrows on networks indicate precedent and flow and can cross over each other.
4. Each activity should have a unique identification number.
5. An activity identification number must be greater than that of any activities that precede it.
6. Looping is not allowed.
7. Conditional statements are not allowed.
8. Where there are multiple starts, a common start node can be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.
When manually creating the network it is customary to include room for the following information for each activity:
Duration
Early start (ES)
Late start (LS)
Early finish (EF)
Late Finish (LF)
The duration of each activity is estimated. With the network and the duration of each task, we can start determining the rest of the information.
Before we begin calculating, there are some other definitions in networks that you need to know:
Path: a sequence of connected, dependent activities
Parallel activities: activities that can take place at the same time, if desired.
Burst activity: an activity that has more than one activity immediately following it (more that one dependency arrow flowing from it)
Merge activity: an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it)
The Critical Path
By definition, the critical path is the longest path through the activity network. By adding the durations along each path we can identify which path(s) are critical. The reason these are “critical” is that if any activity on them is delayed, the project will be delayed. The time required to complete all activities on the critical path is called the critical time.
Other features of the critical path include:
the network path(s) that has (have) the least slack in common
the shortest expected time in which the entire project can be completed
important because it impacts completion time
where you put best people on
where you pay extra attention when doing risk assessment
where you don’t look when other managers are asking to ‘borrow’ people or equipment
where you look when you don’t have time to monitor all activities
Calculating Early Start and Finish
A forward pass through the network (starting from the starting point and going towards the end) can help us determine the earliest times.
Which activities represent the critical path? (critical path—CP)
How soon can the activity start? (early start—ES)
How soon can the activity finish? (early finish—EF)
How soon can the project finish? (expected time—TE)
To perform the forward pass, for each activity you know: ES + Duration = EF. So you just start from the first task, use this formula and carry the early finish (EF) to the next activity where it becomes its early start (ES) unless the next succeeding activity is a merge activity, in which case the largest early finish (EF) number of all its immediate predecessor activities is selected.
Calculating Late Start and Finish
After the forward pass, a backward pass through the network can help us determine the latest times:
How late can the activity start? (late start—LS)
How late can the activity finish? (late finish—LF)
How long can the activity be delayed? (slack or float—SL)
To do this, we know for each activity: LF – Duration = LS. We start from the last task on the critical path and move backward, using this formula to calculate LS. Carry the late start (LS) to the next preceding activity where it becomes its late finish (LF) unless the next succeeding activity is a burst activity, in which case the smallest late start (LS) number of all its immediate successor activities is selected.
Float/Slack
Float or slack are concepts that have to do with the amount of time the activities or the project may be delayed. Tasks on the critical path have zero float. Tasks NOT on the critical path have slack available.
Total float is the amount of time an activity can be delayed from its early start without delaying the project finish date. It provides a measure of high critical each activity is and its potential for delaying the project. It can be calculates as LS – ES or LF – EF. If total float is negative, the project finishes after schedule, which requires either a reschedule or acceptance.
Free float is the amount of time an activity can be delayed without delaying any successor. Having free float allows flexibility in scheduling scarce resources. Only the activity at the end of a chain of activities, where you have a merge activity may have free float.
Safety float is the remaining allowable delay of an activity if all predecessors finish as late as possible.
Network sensitivity is the likelihood the original critical path(s) will change once the project is initiated. A network schedule that has only one critical path and noncritical activities that enjoy significant slack would be labeled ‘insensitive’. Projects are easier to manage when there is project slack. The primary attention of the project manager must be to activities on the critical path. If anything delays one of these activities, the project will be late.
Schedule Contingency (Buffers)
Schedule contingency is extra time added to a project schedule to account for unforeseen delays, risks, and uncertainties. This “buffer time” allows a project to proceed without missing its final deadline when unexpected issues arise, such as supply chain disruptions, personnel shortages, or design changes. It is distinct from standard float and is typically determined through risk analysis. So your schedule should have room for the addition of buffers after risk analysis is complete. Buffers are an insurance policy. You don’t want to use it, but you eventually will.
Some standard methods of buffer addition:
add a percentage to the duration of the task (typically 20%) based on the risk-level
Use 3 point estimation or other probabilistic approaches to determine buffer (we learn about these in estimation)
Schedule contingency can be shown on the schedule in different ways:
Contingency at the end of the schedule
People assume they don’t need to worry
Intermediate milestones less meaningful
Management does not accept it (removes it)
Communicating unrealistic date
Prior to milestones
Added to each task: People use it up, assuming the task should take that long
Create two schedules (one for customers and one for the team)
People feel cheated
Takes more time to create and keep up to date
Do not include contingencies: Too risky
Hide it (but people may spot it)
Benefits of the Network
The project network:
Provides a consistent framework
Ensures proper communication among project stakeholders
Shows interdependences
Identifies critical activities that should not be delayed
Determines expected completion date
Shows which of the activities can be delayed
Determines start dates
Shows which task must be coordinated
Shows which task can be run parallel
Provides the basis for scheduling labor and equipment
Provides the basis for budgeting the cash flow
Shows when resources are needed
Relieves some conflict
Allows probabilistic estimates
Highlights which activities to consider for compressing the project duration
Example
The project has 7 activities (A through G) with the following structure:
Activity
Duration (days)
Predecessors
A
3
— (Start)
B
4
A
C
2
A
D
5
B, C
E
3
C
F
4
D, E
G
2
F
The network diagram for this project looks as follows:
The longest path through this network is the critical path. We can determine this by tracking the different paths:
A → B → D → F → G: 3 + 4 + 5 + 4 + 2 = 18
A → C → D → F → G: 3 + 2 + 5 + 4 + 2 = 16
A → C → E → F → G: 3 + 2 + 3 + 4 + 2 = 14
The first path is the critical path.
We can now track different paths and do the passes. Remember that on the critical path, there is no slack so the early and late dates will be the same. In other words, the critical path will provide a reference for determining the dates for other tasks.
We do a forward pass on the critical path:
Activity
ES = LS
EF = ES + d = LF
A
0
3
B
3
7
D
7
12
F
12
16
G
16
18
Now we can do a foward pass on the other paths to determine the early start and finish for noncritical activities:
Activity
ES
EF = ES + d
C
3
5
E
5
8
Remember that: ES = max ( EF of all predecessors )
Now we do a backward pass to find the late times for the noncritical activities:
Activity
LF
LS = LF − d
E
12
9
C
7
5
Remember that: LF = min ( LS of all successors )
Determining the floats can help us identify the flexibility in the network, and verify that we did not make any mistakes:
Activity
TF = LS − ES
A
0
B
0
C
2
D
0
E
4
F
0
G
0
In summary:
Gannt Chart
The Gannt chart is a type of bar chart, developed by Henry Gantt around 1917, that illustrates a project schedule with the goal of comparing planned and actual progress. These charts display the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. A traditional Gantt chart does not show dependencies but many current Gantt charts add the critical path and arrows to indicate tasks that precede other tasks.
Gannt charts are usually developed based on the network diagram. They are easy to read and are commonly used to display scheduled activities and the current state of a project. However, as the number of activities increases, following a Gannt chart becomes harder.
Evaluating Schedules
A proper project schedule:
Uses WBS (though it may use a limited number of levels depending on the use case of the schedule)
Has assigned responsibility for each task to one person or manager
Has realistic resource requirement when compared to the available resources
Tasks are deliverable-oriented, measurable
Shows milestones which are widely understood and clearly definable
Is base-lined
Shows the deliverables and decisions required from the customer
Shows procurement tasks, lead times, other related requirements
Is based on a critical path network calculation with critical path is clearly traceable
Other tips in developing the schedule include:
If project is not yet approved, timescale by week numbers (not by specific dates) may be preferable
At any fixed time, the concurrent activities should make sense and be independant
Dependencies should be shown on the bar chart, if not too visually crowded
Showing total float may be advisable (depends on the audience)
Contingency times should be shown, preferably before major milestones
After the schedule is developed:
Get approval from sponsor, which may require some negotiations
After approval, develop the project resource plan
Project Resource Planning may cause schedule adjustments
Practical Example: New Student Registration System
Valley college plans to develop a new student registration system. The project manager discusses with the project team and identifies the following list of activities:
A1: Finalize requirements (5 days).
A2: Design database changes (4 days).
A3: Implement database changes (6 days).
A4: Develop web front-end (10 days).
A5: Integration testing (5 days).
A6: User acceptance testing (5 days).
Dependencies:
A1 → A2 → A3 → A5 → A6.
A1 → A4 → A5 → A6.
This network diagram provides the basis for critical path analysis.
Using forward and backward passes:\
Compute earliest and latest start/finish dates for each activity.
Identify the path with zero total float (e.g., A1–A2–A3–A5–A6).
Activities on this path have no slack; delays on them directly delay the project.
Key milestones may look like this:
Requirements Baseline Approved – 30 May 2026.
Design Complete – 30 June 2026.
Build Complete – 30 September 2026.
Pilot Launch – 1 December 2026.
Full Production Launch – 1 June 2027.
Milestone schedules provide a high‑level view of progress for sponsors and can be linked to gate reviews.\