Project Schedule

Learning Objectives

What is the Project Schedule?

The project schedule is an operating timetable for the project. It includes information about:

The project schedule is created after the creation of the WBS and before resource planning: the WBS fully describes the activities that are needed, while the durations selected will link to the resources assigned to the project.

Schedule Creation Processes

In this section, we will summarize the schedule creation processes as described by PMI. Other than Plan Schedule Management, the rest of these processes may be revisited during implementation to adjust the project plan based on changes during the project.

Plan Schedule Management Process

In plan schedule management, the team determines their approach to project scheduling: What form of documentation is used, what assumptions are made and what specific language is used in the project. The process has the following elements:

One of the most important parts of planning schedule management, is deciding on the hierarchy of schedules used by the project. Most projects have a hierarchy of schedules that may include:

As an example, a development of a housing complex with 4 blocks may be considered a program. The program master schedule tells us when each block has to be completed. Each block will then have a project master schedule which tells us when the structure is complete, when sprinklers are installed, etc. The fire safety company which installed the sprinklers when then take that information and created an activity schedule to install the sprinklers. Both the sprinkler company, and the block developer will have their own control schedules to track how they are progressing.

Tools used to communicate the schedule include:

2df7213390f5d3c147f676363e1048f0.png

801ecda75a426185162150a07eea0721.png The Ultimate Guide to Milestone Charts | Motion | Motion (usemotion.com)

Define Activities Process

An activity is an element of the project that requires time but may not require resources. The activity definition process is a further breakdown of the work package elements of the work breakdown structures (WBS). It documents the specific activities needed to fulfill the deliverables detailed in the WBS. These activities are not the deliverables themselves but the individual units of work that must be completed to fulfill the deliverables.

Activity definition uses everything we already know about the project to divide the work into activities that can be estimated. This process includes the following elements:

For example, in a construction project you may have a workpackage which is focused on painting. The paint job can be broken down in different ways. Let’s say we break it down by floor (creating another level in the WBS). Now for completing painting in each floor, there are particular activities that need to happen: area has to be cleaned, primer needs to be applied, paint needs to be applied, etc. These are the activities.

You can see that these activities can be overlapped: you do not need to finish applying primer to all of the floor before you start painting. You could paint an area where primer is applied, while continuing to apply primer elsewhere. That is the whole idea behind this process. By identifying activities at a lower level of detail than the work package, you could see if the work can be done in different ways to make up for time, or money. Of course, if you have a contractor doing this, you as the project manager may just plan the work packages, and have your subcontractor plan the details.

Sequence Activities Process

After the activities are determines, we can sequence them. The aim is to identify how the tasks are related to each other (would one need to be completed after the other one). We also want to identify unrelated tasks which can be completed concurrently.

The process has the following elements:

Activity Durations Process

After determining the sequence of activities, we need to estimated how long the activity will take. It is important to distinguish between the duration of a task and the effort:

Activity durations process has the following elements:

Developing the Schedule Process

This is where the actual schedule is created. It has the following elements:

In the next sections we see how this happens in action.

Logic Networks and Scheduling

The basis of project scheduling are logic networks and precedence diagramming method (PDM). These networks depict the activities and their relationship to each other. There are approaches to precedence diagrams: Activity on Arrow (AOA) and Activity on Node (AON). We will focus on the latter. Network diagram are more technical than other tools such as Gannt charts, and help project managers create a plan. They are not a scaled timeline, which is what most people expect out of a schedule.

Scheduling methods were developed around 1950s. Dupont developed the critical path method (CPM), a method which uses precedence diagrams and deterministic (fixed) time estimates to calculate the start and end dates of each activity. Around the same time, the Program Evaluation and Review Technique (PERT) was developed for the Polaris missile/submarine project which uses probabilistic estimates (a probability distribution) for time estimates. Nowadays, project management software have blended the two approaches.

Creating the Logic Network

The precedence diagram/project network is a graphic flow chart depicting the project activities that must be completed, their logical sequences, the interdependencies of the activities to be completed, and the times for the activities to start and finish along with the longest path(s) through the network—the critical path.

For the simple case of two activities, we start with the activities at the nodes and connect them with an arrow, which depicts the relationship between the two tasks. PDM1.png

The first activity is the predecessor and the one at the end of the arrow is the dependent activity or successor.

The relationship between the two activities is also called their dependency, and is determined based on the nature of the activities and context of the project. Generally speaking, the dependency may be:

The relationships/dependencies themselves are:

By default we assume that the relationship is FS. Any other relationship is explicitly written on the arrow. The goal is not to have too many none-FS relationships, unless it is not possible.

In addition to the dependencies, there might be time delays involved in the network:

Some basic rules for creating project networks: 1. Networks flow typically from left to right. 2. An activity cannot begin until all preceding connected activities have been completed. 3. Arrows on networks indicate precedent and flow and can cross over each other. 4. Each activity should have a unique identification number. 5. An activity identification number must be greater than that of any activities that precede it. 6. Looping is not allowed. 7. Conditional statements are not allowed. 8. Where there are multiple starts, a common start node can be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.

When manually creating the network it is customary to include room for the following information for each activity:

The duration of each activity is estimated. With the network and the duration of each task, we can start determining the rest of the information.

Before we begin calculating, there are some other definitions in networks that you need to know:

The Critical Path

By definition, the critical path is the longest path through the activity network. By adding the durations along each path we can identify which path(s) are critical. The reason these are “critical” is that if any activity on them is delayed, the project will be delayed. The time required to complete all activities on the critical path is called the critical time. Other features of the critical path include:

Calculating Early Start and Finish

A forward pass through the network (starting from the starting point and going towards the end) can help us determine the earliest times.

To perform the forward pass, for each activity you know: ES + Duration = EF. So you just start from the first task, use this formula and carry the early finish (EF) to the next activity where it becomes its early start (ES) unless the next succeeding activity is a merge activity, in which case the largest early finish (EF) number of all its immediate predecessor activities is selected.

Calculating Late Start and Finish

After the forward pass, a backward pass through the network can help us determine the latest times:

To do this, we know for each activity: LF – Duration = LS. We start from the last task on the critical path and move backward, using this formula to calculate LS. Carry the late start (LS) to the next preceding activity where it becomes its late finish (LF) unless the next succeeding activity is a burst activity, in which case the smallest late start (LS) number of all its immediate successor activities is selected.

Float/Slack

Float or slack are concepts that have to do with the amount of time the activities or the project may be delayed. Tasks on the critical path have zero float. Tasks NOT on the critical path have slack available.

Total float is the amount of time an activity can be delayed from its early start without delaying the project finish date. It provides a measure of high critical each activity is and its potential for delaying the project. It can be calculates as LS – ES or LF – EF. If total float is negative, the project finishes after schedule, which requires either a reschedule or acceptance.

Free float is the amount of time an activity can be delayed without delaying any successor. Having free float allows flexibility in scheduling scarce resources. Only the activity at the end of a chain of activities, where you have a merge activity may have free float.

Safety float is the remaining allowable delay of an activity if all predecessors finish as late as possible.

Network sensitivity is the likelihood the original critical path(s) will change once the project is initiated. A network schedule that has only one critical path and noncritical activities that enjoy significant slack would be labeled ‘insensitive’. Projects are easier to manage when there is project slack. The primary attention of the project manager must be to activities on the critical path. If anything delays one of these activities, the project will be late.

Schedule Contingency (Buffers)

Schedule contingency is extra time added to a project schedule to account for unforeseen delays, risks, and uncertainties. This “buffer time” allows a project to proceed without missing its final deadline when unexpected issues arise, such as supply chain disruptions, personnel shortages, or design changes. It is distinct from standard float and is typically determined through risk analysis. So your schedule should have room for the addition of buffers after risk analysis is complete. Buffers are an insurance policy. You don’t want to use it, but you eventually will.

Some standard methods of buffer addition:

Schedule contingency can be shown on the schedule in different ways:

Benefits of the Network

The project network:

Example

The project has 7 activities (A through G) with the following structure:

Activity Duration (days) Predecessors
A 3 — (Start)
B 4 A
C 2 A
D 5 B, C
E 3 C
F 4 D, E
G 2 F

The network diagram for this project looks as follows: CPM_example.png The longest path through this network is the critical path. We can determine this by tracking the different paths:

  1. A → B → D → F → G: 3 + 4 + 5 + 4 + 2 = 18
  2. A → C → D → F → G: 3 + 2 + 5 + 4 + 2 = 16
  3. A → C → E → F → G: 3 + 2 + 3 + 4 + 2 = 14

The first path is the critical path.

We can now track different paths and do the passes. Remember that on the critical path, there is no slack so the early and late dates will be the same. In other words, the critical path will provide a reference for determining the dates for other tasks.

We do a forward pass on the critical path:

Activity ES = LS EF = ES + d = LF
A 0 3
B 3 7
D 7 12
F 12 16
G 16 18

Now we can do a foward pass on the other paths to determine the early start and finish for noncritical activities:

Activity ES EF = ES + d
C 3 5
E 5 8

Remember that: ES = max ( EF of all predecessors )

Now we do a backward pass to find the late times for the noncritical activities:

Activity LF LS = LF − d
E 12 9
C 7 5

Remember that: LF = min ⁡ ( LS of all successors )

Determining the floats can help us identify the flexibility in the network, and verify that we did not make any mistakes:

Activity TF = LS − ES
A 0
B 0
C 2
D 0
E 4
F 0
G 0

In summary: CPM_example_Solved.png

Gannt Chart

The Gannt chart is a type of bar chart, developed by Henry Gantt around 1917, that illustrates a project schedule with the goal of comparing planned and actual progress. These charts display the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. A traditional Gantt chart does not show dependencies but many current Gantt charts add the critical path and arrows to indicate tasks that precede other tasks.

Gannt charts are usually developed based on the network diagram. They are easy to read and are commonly used to display scheduled activities and the current state of a project. However, as the number of activities increases, following a Gannt chart becomes harder.

90918bd6ef8dbc750efa1c191cb80fb9.png

Evaluating Schedules

A proper project schedule:

Other tips in developing the schedule include:

After the schedule is developed:

Practical Example: New Student Registration System

Valley college plans to develop a new student registration system. The project manager discusses with the project team and identifies the following list of activities:

Dependencies:

This network diagram provides the basis for critical path analysis.

Using forward and backward passes:\

Key milestones may look like this:

Milestone schedules provide a high‑level view of progress for sponsors and can be linked to gate reviews.\

Summary

Practice and Examples