The Planning Processes

After the project charter is approved, the Project Initiation phase is complete and you are ready to proceed to the Project Planning process group.

One can think of two extremes when it comes to planning:

The purpose of the planning process group is to:

The Planning Process Group includes the following processes:

These various processes and plans impact each other, so you need to iterate! You also notice above that many of the processes including their own planning phase (for example plan resource management happens before estimating activity resources). The general idea in project management is “planning prevents poor performance”, but also “planning planning prevents poor performance”!

846833d12b8cd7f8b2fe804d89cda048.png

Collaborative Planning

Project management planning is not just completed by the project manager. The project manager ensures that all processes are complete and relevant stakeholders are engaged in the process. This is a collaborative process so those affected should be involved. It is a process that requires realistic goals and tasks. In this process, past information is used but are not the only source of information. The team works together to identify alternatives and ensure a feasible plan is developed.

Collaborative planning allows for:

The Project Management Plan

The project management plan defines HOW the project is executed, monitored and controlled, and closed. It includes:

The Develop Project Management Plan process involves the following elements:

Common issues in project planning which can lead to project failure include:

Planning 101

Before we delve into the details, it helps to get a high level view of planning.PM101 Estimating | PMI summarizes it as shown below: planning101.png

  1. Clarify project requirements and expectations, prepare an overview definition of the project, identify potential alternative solutions, assumptions, constraints, etc.
  2. Make rough top-down estimates (starting with the project and then breaking down at least one level): You may use past projects or assigned budget to identify what the cost should be or how it should be broken down
  3. Develop work breakdown structure: This allows us to identify the activities that need to take place
    • Major categories of work (3 to 8 max)
    • Main activities or work packages in each category (max 60) and identify who is responsible for each
    • Identify who should be involved in estimating the work packages
  4. Develop flowchart of activities: This allows us to understand the order in which the work needs to take place
  5. Estimate the time needed for each activity: Use historical records, expert judgment, analogous activities, and take into account resource availability, and capability (type and level of skills). Choosing between duration‑driven and effort‑driven scheduling affects resource assignments, overlaps with other projects, and the feasibility of meeting external deadlines.
    • Duration-driven scheduling: You define the duration, calendar and the resource, and the effort gets calculated. For example, Task A must finish in 5 days, with one full-time person → effort = 40 hours..
    • Effort-driven scheduling: You define the effort, people and the calendar, and the duration gets calculated. For example, Task B needs 40 hours of effort and can have 2 people half-time → duration = 5 days.
  6. Perform critical path analysis: We learn about this later but this analysis allows us to take into account the duration and order of the activities to determine the total amount of time the project will take
    1. Estimate costs bottom up (resources, infrastructure, equipment, materials,maintenance, operations, overhead): Here you are taking into account the details of your plan.
  7. Reconcile differences between top-down and bottom-up estimates and align with the timeline and budget: For now you disregard predetermined project time and budget requirements. Now we need to understand how we can meet those constraints: Do the differences make sense? If the project costs too much, can we reduce the scope or performance? Or can we ask for more budget? What are the risks involved in the project? Did you take into account all risks? Do you need additional reserves?

Example: Valley College Registration System: Collaborative Planning Workshop

Let’s go back to the case of creating a new registration system for Valley College. The project manager holds a half‑day planning workshop with:

Summary

Bibliography

The following sources were also consulted in creating this resource: