After a project is selected to move forward, we would start the initiation process group. The initiation process group has two main processes:
Develop project charter
Identify Stakeholders
At this stage, based on the original project proposal we know:
The business problem or opportunity
The general solution
The business case
And if this information is not available, then we have to determine it.
The goal of initiation is to:
Document that information and form the project (through the project charter)
Appoint the project team and identify stakeholders
The information gathered forms the basis of the rest of project planning.
The Project Charter
A project charter, project definition, or project statement is a document that authorizes the project manager to initiate and lead the project, It often includes a brief scope description as well as such items as risk limits, business case, spending limits, roles and responsibilities, objectives and the main stakeholders. It ensures everyone has the same understanding of the project, by clarifying:
Reasons for undertaking project and its justification
Objectives and constraints, outlining the general scope of the project
Directions concerning the solution
Identities of the main stakeholders and who has authority to approve the charter and project outcomes
The project manager and his or her authority level
The project charter is used by the project manager during the planning process.
Before the project charter is created there may already be a needs assessment, feasibility study, an RFP or contract from external customer, or some form of “Project Statement of Work” or proposal that is linked to a business need/case/justification, the organizations strategic goals, and outlines the initial scope description (requirements & characteristics).
Inputs: This are the items that need to be consulted in creating the project charter.
Business documents such as the business case or the benefits management plan
Organizational agreements relevant to the project
Enterprise environmental factors: These include internal elements such as organizational culture, structure, facilities, resources, and tools alongside external elements such as market considerations, regulatory requirements, social and cultural influences and financial considerations relevant to the project.
Organizational process assets: This is the internal accumulated knowledge, processes and information the organization has access to. It may include intellectual property, documentation from past projects, lessons learned, policies and any other knowledge retained in the organization.
Tools & Techniques: Charters are developed mainly relying on expert judgment, data gathering (through brainstorming, focus groups, interviews and surveys), interpersonal and team skills (to facilitate discussions and manage conflict), and meetings.
Outputs: The project charter is the main output, along with an assumption log documenting major assumptions.
The project charter is a key document, as it is the main input document for all planning processes for the project. There is no specific standard way to create a project charter, and many templates could be found online. A typical outline will include the following information:
Project approval requirements and success criteria (i.e., what constitutes success, who decides the project is successful, who signs off on the project)
Project exit criteria (i.e., what are the conditions to be met in order to close or to cancel the project or phase)
Related documents
Project organizational structure
The project manager assigned to the project, their responsibility, and authority level
Project authorization (Name and authority of the sponsor or other person(s) authorizing the project charter)
It is generally suggested that the Charter is made as SMART as possible:
Specific: Be specific in targetting an objective
What do we want to accomplish?
Why are we undertaking this project?
Who is involved or will be affected by the project?
Where will this project be conducted?
Which constraints (scope, time, money, risk, etc.) have been placed on our project?
Measurable: Estabilish measurable indicators of progress
How will project progress and success be measured?
What will be the measurable difference once our project is completed successfully?
Assignable: Make the objectives assignable to one person for accountability
Who will do the work?
Can people who have the expertise in the organization be identified to complete this work?
Can the expert be hired from outside of the organization?
Realistic: Is it realistic that the organization can achieve this project, given its talents and resources?
Time Related: When will the project be completed and how long will it take?
If the description for a project does not meet all these criteria, then it is time to go back to the drawing board and make sure that what is being described is really a project, rather than a program or strategic goal.
It is also beneficial to understand the core priorities of the project.Three major criteria (trade-offs) that a project manager has to manage are: Cost (budget), Time (schedule), Performance (scope). As a project manager, you need to understand whether these are a:
Constraint: the original parameter is fixed. For example, your project may have a fixed end date or fixed resources.
Enhanceable: A criterion should be optimized. For example, you may be given 10 resources, but using less is better.
Acceptable: A criterion is tolerable not to meet the original parameter. For example, the timeline proposed may be 10 months, but you can exceed the timeline if needed.
These considerations form the project priority matrix.
Once the project charter is approved, a launch/kick-off meeting is scheduled. The goal of this meeting is to ensure:
The project team and the project sponsor (and potentially other stakeholders) have the same understanding of the project scope and other elements of the project charter
Various senior managers understand their responsibilities and have committed to develop an initial task and resource plan
Any potential benefits to the organization outside the scope are noted
Anything atypical about the project is highlighted
The project kick-off is the basis to document any clarifications before the team starts work on the project.
A kick-off meeting agenda might look like this:
Welcome & Introductions
Introduce project team members
Introduce client / stakeholder representatives
Review roles and responsibilities
Project Overview
Background and context
Problem statement / opportunity
Project objectives
Expected outcomes and success criteria
Scope & Deliverables
In-scope items
Out-of-scope items
Major deliverables
Assumptions and constraints
Schedule & Milestones
High-level timeline
Key milestones
Critical dependencies
Governance & Communication
Decision-making structure
Reporting cadence
Communication channels
Escalation paths
Risks & Issues
Initial risk identification
Known issues
Mitigation strategies
Tools & Ways of Working
Collaboration tools
Document management
Meeting norms
Change control process
Next Steps
Immediate actions
Responsibilities
Upcoming meetings
Q&A / Open Discussion
Closing Remarks
Summary of agreements and action items
Confirmation of next meeting
Example Project Charter – Online Course Registration System
Note: The level of detail in a Project Charter and sections are highly dependent on the nature of the project and the organization you work on. This is just to give you an example for a small project.
Background and Business Case
Valley College relies on in‑person and paper-based registration, leading to long queues, manual errors, and delayed reporting. An online registration system is proposed to improve student experience and operational efficiency.
Purpose and Objectives:
Implement a web-based system for course search and registration.
Reduce average registration wait time from 45 minutes to under 5 minutes in the next registration cycle.
Achieve at least 80% of registrations processed through the online system within one year of launch.
Reduce manual registration errors by 90% compared to the previous semester.
High-Level Deliverables
Requirements specification and system design.
Deployed web application integrated with the student information system.
Training materials and sessions for staff and students. - Support procedures and documentation.
Scope and Boundaries
In scope: Online course add/drop, enforcement of pre‑requisites and capacity limits, email confirmations, integration with existing SIS.
Out of scope: Native mobile apps, redesign of SIS, changes to academic policies.
Key Requirements
The system shall enforce pre‑requisites and maximum enrolment limits.
The system shall provide confirmation emails for successful registrations and waitlist placements.
Budget and Pre‑Approved Financial Resources
Estimated total budget: CAD 250,000.
Initial approved funding: CAD 200,000, with contingency of CAD 25,000, and management reserve of CAD 25,000 subject to change control
Key Risks (High-Level)
Technical integration issues with legacy SIS.
Resistance from staff accustomed to manual processes.
Performance risks during peak registration periods.
Assumptions, Constraints, Dependencies
Assumes continued use of the current SIS for at least 3 years.
Constraint: System must be live before the Fall 2027 registration period.
Dependency: Availability of IT infrastructure and authentication services from central IT.
Project Approval Requirements and Success Criteria
Registrar and CIO sign‑off on scope and requirements.
Successful pilot with at least 500 students and <2% error rate.
Post‑implementation survey showing ≥80% student satisfaction with registration experience.
Authority and Approval
Project Manager Authority Level- Authorized to assign project team members within agreed resource limits; request change control for scope, schedule, and budget adjustments; and approve expenditures up to CAD 20,000 per line item within the approved budget.
Sponsor Authorization: “I hereby authorize the Online Course Registration System project and assign the Project Manager named above to lead this initiative within the constraints and objectives described in this charter.”
The charter authorizes the project manager to use organizational resources within defined constraints and serves as the basis for detailed planning.
Stakeholder Identification
Stakeholders are people, groups or organizations that could impact or be impacted by the project. Examples include:
The project team (project team members and project managers)
The project sponsor
Customers/users
Sellers
Business partners
Operations management
Functional managers
Project Management Office
Program Manager
Portfolio Managers
Unions
Activities
Regulatory Bodies
Governing bodies
Others (the public, landowners, interest groups, business competitors)
As part of project initiation, it is important to identify stakeholders so they can be consulted while the planning of the project, if needed.
Business documents (Business case, benefits management plan)
Project documents (Change log, Issue log and Requirements documentation): Note that these do not exist at the start of the project but are created later on.
Organizational agreements
Enterprise environmental factors
Organizational process assets
Tools & Techniques: Stakeholder identification relies on expert judgment, data gathering (through questionnaires and surveys, brainstorming and interviews), data analysis (particularly stakeholder analysis and document analysis), data representation (particularly stakeholder mapping/representation) and meetings.
Outputs:
Stakeholder register
Project management plan updates (requirements management plan, communications management plan and stakeholder engagement plan)
Note that stakeholder identification is not a one time process. Throughout the project, it is important to consistently identify any new relevant stakeholders and determine how to engage them.
The key output of stakeholder identification is the stakeholder register. This document is used throughout the project to inform interactions with the stakeholders. It lists all stakeholders and stakeholder groups with their interests, involvement, interdependencies, influence on project success, interactions with the stakeholders (whether planned or not), and person responsible for the stakeholder on the team. The stakeholder register is continuously updated throughout the project life, and is closely related to the project communication plan.
A typical stakeholder register will include the following information:
Stakeholder Name
Key interests and issues
Abilities
Level of interest
Level of power
Will their interest level vary throughout the project?
Can coalitions be built?
Communication strategy
Actions desired from this stakeholder
To create the stakeholder register, first one need to identify stakeholders: This is usually achieved through the expert judgment of project manager and his team. While it is fine to start with general categories, the more specific you can be about stakeholders, the better you can plan.
Next the stakeholders need to be understood, analyzed and prioritized. The first step in this process is understanding the interests of the stakeholders: Why do they care about your project? You should also think about what you want or need from each stakeholder. Armed with this information, three common methods to analyze stakeholders are:
Power-Interest Grid: The power of the stakeholders and their interests in the project are rated (either through numbers or through high/low). This can be used to map the stakeholders onto a power-interest grid which can help in selecting a communication approach:
High interest and power must be fully engaged and managed closely (Engage frequently - Involve in decision-making - Provide detailed updates)
High power and low interest must be kept satisfied (Provide high-level updates - Address concerns proactively - Avoid overwhelming with detail)
Low power and high interest must be kept informed (Share regular updates - Provide opportunities for feedback - Maintain transparency)
Low power and low interest must be monitored (Monitor periodically - Communicate only as needed)
Commitment Assessment Matrix: Stakeholders may be analyzed using a scale of strongly opposed to strongly supporting, or Unaware, Resistant, Neutral, Supportive, Leading. This can inform the level and frequency of communication.
Stakeholder
Unaware/Strongly Opposed
Resistant/Opposed
Neutral
Supportive
Leading / Strongly Support
S1
Current
Desired
S2
Current
Desired
Cooperation-Threat Matrix: This method categorizes stakeholders based on the threat they post to the project and their potential for cooperation:
If the potential for threat and cooperation are both low, the stakeholder should be monitors.
If the potential for threat is low and cooperation is high, then these are supportive stakeholders that should be involved in the project.
If the potential for threat is high and cooperation is low, these are non-supportive stakeholders that should be defended against.
If the potential for threat and cooperation is high, these stakeholders should be collaborated with.
These analysis will allow you to decide how to communicate with the stakeholders, and whether there are opportunities to partner with specific stakeholders, or to turn them into supportive stakeholders.
Example: Stakeholder Register (Excerpt)
Stakeholder
Role
Interest
Power
Key Concerns
Engagement Strategy
Registrar
Sponsor
High
High
Student experience, accuracy
Manage closely
CIO
Executive stakeholder
Medium
High
Integration, security, capacity
Keep satisfied
Academic Deans
Functional stakeholders
Medium
Medium
Course capacity, policy enforcement
Consult regularly
Students’ Union
User representative
High
Low–M
Ease of use, fairness
Keep informed, interactive
The Communication Plan
In most cases, the stakeholder analysis forms the basis for the project communication plan, which addresses the following questions:
What information needs to be collected, what do they need/want to know and when/how frequently?
Who will receive the information?
What methods will be used to gather and store information?
What are the limits, if any, on who has access to certain kinds of information?
When will the information be communicated?
How will it be communicated? (what method(s) do they prefer? Are there methods that are unsuitable)
Who will be the contact point from the project for this communication?
Stakeholder analysis helps you identify different groups with different communication needs and also sources of information. Information communicated during a project include project status reports, deliverable issues, changes in scope, team status meetings, gating decisions, accepted request changes, action items, and milestone reports.
The form of communication should be analyzed as well:
Formal verbal communication through presentations, project reviews, briefings, product demos, brainstorming or meetings
Informal verbal communication through conversations or ad hoc discussions
Formal written communication in the form of progress reports, project documents, business case
Informal written communication in the form of brief notes, Email, instant messaging/texting, or social media
Nowadays, an important factor is also providing access to information, be it through a website or a shared folder. Another factor is whether synchronous or asynchronous communication is a better choice.
Finally, the project needs to assign communication and engagement to someone on the team, and determine how regularly stakeholders should be engaged.
Example:
What Information
Target Audience
When?
Method of Communication
Provider
Milestone report
Senior management and project manager
Bimonthly
E-mail and hardcopy
Project office
Project status reports & agendas
Staff and customer
Weekly
E-mail and hardcopy
Project manager
Team status reports
Project manager and project office
Weekly
E-mail
Team recorder
Issues report
Staff and customer
Weekly
E-mail
Team recorder
Escalation reports
Staff and customer
When needed
Meeting and hardcopy
Project manager
Outsourcing performance
Staff and customer
Bimonthly
Meeting
Project manager
Accepted change requests
Project office, senior mgmt., customer, staff, and project mgr.
Anytime
E-mail and hardcopy
Design department
Oversight gate decisions
Senior management and project manager
As required
E-mail meeting report
Oversight group or project office
Sample Stakeholder Register
Project Information
Project Name:
Project Manager:
Date Created:
Last Updated:
1. Stakeholder Identification
Stakeholder Name
Role / Position
Organization
Contact Information
Category (Internal/External)
2. Stakeholder Assessment
Stakeholder Name
Interest in Project
Influence / Power
Impact
Expectations
Attitude (Supportive/Neutral/Resistant)
3. Stakeholder Classification
Stakeholder Name
Power
Interest
Engagement Level (Current)
Engagement Level (Desired)
Strategy
High/Med/Low
High/Med/Low
Unaware / Resistant / Neutral / Supportive / Leading
Same scale
Engagement strategy summary
4. Communication Requirements
Stakeholder Name
Communication Needs
Frequency
Format / Channel
Owner
5. Notes & Additional Considerations
Risks related to stakeholder engagement:
Opportunities from stakeholder involvement:
Special considerations (cultural, regulatory, political):