ProjectManagementOER

Project Initiation

Learning Objectives

By the end of this unit, you should be able to:

The Initiation Process Group

After a project is selected to move forward, we would start the initiation process group. The initiation process group has two main processes:

At this stage, based on the original project proposal we know:

And if this information is not available, then we have to determine it.

The goal of initiation is to:

The information gathered forms the basis of the rest of project planning.

The Project Charter

A project charter, project definition, or project statement is a document that authorizes the project manager to initiate and lead the project, It often includes a brief scope description as well as such items as risk limits, business case, spending limits, roles and responsibilities, objectives and the main stakeholders. It ensures everyone has the same understanding of the project, by clarifying:

Before the project charter is created there may already be a needs assessment, feasibility study, an RFP or contract from external customer, or some form of “Project Statement of Work” or proposal that is linked to a business need/case/justification, the organizations strategic goals, and outlines the initial scope description (requirements & characteristics).

Based on the Process Groups: A Practice Guide, the “develop project charter” process has the following components:

The project charter is a key document, as it is the main input document for all planning processes for the project. There is no specific standard way to create a project charter, and many templates could be found online. A typical outline will include the following information:

It is generally suggested that the Charter is made as SMART as possible:

If the description for a project does not meet all these criteria, then it is time to go back to the drawing board and make sure that what is being described is really a project, rather than a program or strategic goal.

It is also beneficial to understand the core priorities of the project.Three major criteria (trade-offs) that a project manager has to manage are: Cost (budget), Time (schedule), Performance (scope). As a project manager, you need to understand whether these are a:

Once the project charter is approved, a launch/kick-off meeting is scheduled. The goal of this meeting is to ensure:

A kick-off meeting agenda might look like this:

  1. Welcome & Introductions
    • Introduce project team members
    • Introduce client / stakeholder representatives
    • Review roles and responsibilities
  2. Project Overview
    • Background and context
    • Problem statement / opportunity
    • Project objectives
    • Expected outcomes and success criteria
  3. Scope & Deliverables
    • In-scope items
    • Out-of-scope items
    • Major deliverables
    • Assumptions and constraints
  4. Schedule & Milestones
    • High-level timeline
    • Key milestones
    • Critical dependencies
  5. Governance & Communication
    • Decision-making structure
    • Reporting cadence
    • Communication channels
    • Escalation paths
  6. Risks & Issues
    • Initial risk identification
    • Known issues
    • Mitigation strategies
  7. Tools & Ways of Working
    • Collaboration tools
    • Document management
    • Meeting norms
    • Change control process
  8. Next Steps
    • Immediate actions
    • Responsibilities
    • Upcoming meetings
  9. Q&A / Open Discussion
  10. Closing Remarks
    • Summary of agreements and action items
    • Confirmation of next meeting

Example Project Charter – Online Course Registration System

Note: The level of detail in a Project Charter and sections are highly dependent on the nature of the project and the organization you work on. This is just to give you an example for a small project.

Background and Business Case

Valley College relies on in‑person and paper-based registration, leading to long queues, manual errors, and delayed reporting. An online registration system is proposed to improve student experience and operational efficiency.

Purpose and Objectives:

High-Level Deliverables

Scope and Boundaries

Key Requirements

Budget and Pre‑Approved Financial Resources

Key Risks (High-Level)

Assumptions, Constraints, Dependencies

Major Stakeholders

Major Milestones (High‑Level Schedule)

Project Approval Requirements and Success Criteria

Authority and Approval

The charter authorizes the project manager to use organizational resources within defined constraints and serves as the basis for detailed planning.

Stakeholder Identification

Stakeholders are people, groups or organizations that could impact or be impacted by the project. Examples include:

As part of project initiation, it is important to identify stakeholders so they can be consulted while the planning of the project, if needed.

Based on the Process Groups: A Practice Guide, the “identify stakeholders” process has the following components:

Note that stakeholder identification is not a one time process. Throughout the project, it is important to consistently identify any new relevant stakeholders and determine how to engage them.

The key output of stakeholder identification is the stakeholder register. This document is used throughout the project to inform interactions with the stakeholders. It lists all stakeholders and stakeholder groups with their interests, involvement, interdependencies, influence on project success, interactions with the stakeholders (whether planned or not), and person responsible for the stakeholder on the team. The stakeholder register is continuously updated throughout the project life, and is closely related to the project communication plan. A typical stakeholder register will include the following information:

To create the stakeholder register, first one need to identify stakeholders: This is usually achieved through the expert judgment of project manager and his team. While it is fine to start with general categories, the more specific you can be about stakeholders, the better you can plan.

Next the stakeholders need to be understood, analyzed and prioritized. The first step in this process is understanding the interests of the stakeholders: Why do they care about your project? You should also think about what you want or need from each stakeholder. Armed with this information, three common methods to analyze stakeholders are:

Stakeholder Unaware/Strongly Opposed Resistant/Opposed Neutral Supportive Leading / Strongly Support
S1 Current     Desired  
S2     Current   Desired

These analysis will allow you to decide how to communicate with the stakeholders, and whether there are opportunities to partner with specific stakeholders, or to turn them into supportive stakeholders.

Example: Stakeholder Register (Excerpt)

Stakeholder          Role                 Interest Power Key Concerns                     Engagement Strategy     
Registrar Sponsor  High  High Student experience, accuracy Manage closely
CIO  Executive stakeholder Medium  High  Integration, security, capacity  Keep satisfied
Academic Deans   Functional stakeholders Medium Medium Course capacity, policy enforcement Consult regularly 
Students’ Union   User representative  High    Low–M Ease of use, fairness            Keep informed, interactive

The Communication Plan

In most cases, the stakeholder analysis forms the basis for the project communication plan, which addresses the following questions:

Stakeholder analysis helps you identify different groups with different communication needs and also sources of information. Information communicated during a project include project status reports, deliverable issues, changes in scope, team status meetings, gating decisions, accepted request changes, action items, and milestone reports.

The form of communication should be analyzed as well:

Finally, the project needs to assign communication and engagement to someone on the team, and determine how regularly stakeholders should be engaged.

Example:

What Information Target Audience When? Method of Communication Provider
Milestone report Senior management and project manager Bimonthly E-mail and hardcopy Project office
Project status reports & agendas Staff and customer Weekly E-mail and hardcopy Project manager
Team status reports Project manager and project office Weekly E-mail Team recorder
Issues report Staff and customer Weekly E-mail Team recorder
Escalation reports Staff and customer When needed Meeting and hardcopy Project manager
Outsourcing performance Staff and customer Bimonthly Meeting Project manager
Accepted change requests Project office, senior mgmt., customer, staff, and project mgr. Anytime E-mail and hardcopy Design department
Oversight gate decisions Senior management and project manager As required E-mail meeting report Oversight group or project office

Sample Stakeholder Register

Project Information

1. Stakeholder Identification

Stakeholder Name Role / Position Organization Contact Information Category (Internal/External)
         

2. Stakeholder Assessment

Stakeholder Name Interest in Project Influence / Power Impact Expectations Attitude (Supportive/Neutral/Resistant)
           

3. Stakeholder Classification

Stakeholder Name Power Interest Engagement Level (Current) Engagement Level (Desired) Strategy
  High/Med/Low High/Med/Low Unaware / Resistant / Neutral / Supportive / Leading Same scale Engagement strategy summary

4. Communication Requirements

Stakeholder Name Communication Needs Frequency Format / Channel Owner
         

5. Notes & Additional Considerations

6. Version History

Version Date Changes Author
       

Summary

Practice

Bibliography