Project Selection

Learning Objectives

By the end of this unit, you should be able to:

Where do projects come from?

Before we delve into project management processes, it is beneficial to consider where projects come from. Projects arise owing to the strategic management process, the process of assessing “what we are” and deciding and implementing “what we intend to be and how we are going to get there.” This is a continuous, iterative process aimed at developing an integrated and coordinated long-term plan of action.

The strategic management process can be broken down into four steps:

  1. Review and define the organizational mission: Regularly, organizations review and define their mission and vision based on the internal environment (strengths and weaknesses) and external environment (opportunities and threats). Through this process, the organization understands “what we are now” and defines a mission: “what we want to become.”  Mission statements identify the scope of the organization’s activities in terms of its product and service.
  2. Analyze and formulate strategies: Based on the mission, the organization formulates a strategy: what needs to be done to achieve its mission. Strategy formulation includes determining and evaluating alternative approaches that support the organization’s mission and selecting the best alternatives.
  3. Set objectives to achieve strategies: Objectives translate the organization strategy into specific, concrete, measurable term, and answers the question “how are we going to get there”. Through this process you create a portfolio of strategic choices.
  4. Implement strategies through projects: Implementation answers the question of how strategies will be realized, given available resources. Usually the strategic choices give rise to project options, and organizations need to select the best projects to focus on. These projects are run in tandem with standard operations to help achieve strategic goals.

So projects arise due to an organization’s strategy, and need to be aligned with its strategic goals. Project managers need to understand their organization’s mission and strategy so they can:

Based on experience, successful projects:

The Project Management Office (PMO)

Due to the importance of projects in most organizations, some organizations create a centralized unit or a department that oversees and supports the execution of projects. These PMOs can take on various roles, including:

Seven out of 10 organizations have PMOs, although the name of the organizational unit can differ in different organizations. PMOs tend to help organizations improve their maturity on a scale like the one below:

  1. Ad hoc/Initial: Disorganized with no formal process, accidental successes and failures relying on specific individuals involved
  2. Managed/Repeatable/Structured: Some processes exist (perhaps at project or program level) but these are inconsistently used and results are unpredictable
  3. Defined/standardized: Standardized processes exist and are followed, leading to more predictable results. Integrated system for tracking and managing may exist but are not consistently used
  4. Quantitatively Managed: Processes are controlled and measured, with results more in line with plans
  5. Optimizing: Continuous improvement is taking place by tracking historical project data, success is normal, and performance keeps improving

According to Process Groups: A Practice Guide, there are several types of PMOs in organizations. Each type varies in the degree of control and influence it has on projects within the organization, such as:

Summary: strategy → portfolio → programs/projects → PMO support

Project Portfolio Management

  1. Identify (projects, programs, non-projects)
  2. Categorize: Locate project at the right place for coordination
  3. Evaluate and prioritization
    • Limit no. projects for focus and fit
    • Identify co-dependant projects
    • Eliminate high risk low return
    • Eliminate projects that skip the formal selection process
  4. Balance the portfolio
    • Keep from overloading the organization
    • To balance the resources with needs
    • To balance returns
    • To balance short-, medium-, and long-term returns
  5. Authorize projects

Doing projects right is project management. Doing the right projects is project portfolio management

Why do we need portfolio management?

Project Selection

With organizations having limited resources, and a political environment, not all possible projects are implemented. Organizations need to screen various projects and select those that best align with the organization’s strategy.

When a project idea is conceptualized, both its costs and benefits are uncertain. There is also uncertainty about timing (whether the project will be completed on time) and scope (what will be accomplished). Organizations need to control the level of uncertainty in their activities, and as such they rely on selecting the right mix of projects to get involved in.

Project selection aims to identify the projects that are more beneficial for the organization. Usually this involves answering questions like:

  1. Is the project potentially profitable?
  2. Is the project required?
  3. Does our firm have the skills to complete the project ?
  4. Does the project involve building strategic competencies?
  5. Does the organization have capacity to carry out the project ?
  6. Can project be economically successful? These need to be answered before the project starts and a PM is appointed!

An organization then creates a portfolio of projects. Balancing the number and types of projects is key to the success of the organization. Misaligned portfolios:

Proposing projects

Before projects can be selected, they need to be conceptualized and proposed. Depending on the organization, there are regular processes that lead to the conception of new projects, with someone assigned to lead the project conception process. This leader is usually asked to make their case by submitting a project proposal/overview, which typically:

This description should meet the SMART criteria:

If the description for a project does not meet all these criteria, then it is time to go back to the drawing board and make sure that what is being described is really a project, rather than a program or strategic goal

Project Classification

Most organizations develop a system to classify their projects, in order to better prioritize project choices. One method of classification categorizes projects into:

Another approach is breaking down projects into four categories based on how extensive of a change in product and process is involved:

Another approach is separating projects in terms of degrees of difficulty and commercial value:

63b5ed8376b0da204f6d554a5b0d263d.png

Organizations will consider the number of each type of these projects that they are involved in and aim to balance their focus based on the risk-level and interests, as part of portfolio management. This may be done as part of project selection, or as a screening step before the project selection process is followed.

48399db3876d62f06730c06a95b9ec48.png

How Are Projects Selected?

After a set of possible projects are identified, they need to be assessed based on a set of criteria. Organizations need to define their assessment criteria before any analysis is performed. The selection process acts like a sieve: the aim is to narrow down the number of options to a manageable set that meets the organization’s resource limitations.

Project selection usually involves the following steps:

  1. Create a selection model: This includes identifying the selection criteria aligned with the current organization strategies in consultation with senior management, and how these criteria are used in the selection process.
  2. Source and solicit project proposals: This may involve an internal call for proposals in your organization or an external Request for Proposal (RFP) for external contractors and vendors.
  3. Ranking proposal: In this step, each proposal is evaluated in terms of feasibility, potential contribution to strategic objectives, and fit within a portfolio of current projects. Scores are calculated based on criteria you defined in your selection model. As an option, the team may request additional information before finalizing their prioritization. Some organizations break step 3 into two steps: 3a. Getting an initial proposal with a high-level concept of the project. At this stage some proposals will be rejected based on one set of criteria and shortlist is created. 3b. A project manager and staff is assigned to short-listed proposals to develop a detailed implementation plan, which is the basis of project selection.
  4. Select projects: At this point projects are accepted or rejected based on their score in the model, and the mix in the current portfolio, or directives from senior management. While the goal is to rely objectively on the selection model, in most cases other factors need to be considered to maintain good diversity in the project portfolio. Based on availability of resources, some selected projects may also be put on hold until resources become available.
  5. Decide whether the project fits with the organization strategy: This is key to ensure that the end result makes sense. Portfolios regularly (usually annually) go through these steps to balance the available organizational resources (people and capital) among the different types of projects. There may be the need to stop some projects, or start new ones based on the priorities of the organization.

Organizations with good governance processes also ensure that the priority of each project is published, the selection process is transparent and free of power politics, the progress of current projects is monitored, and that the external environment is continuously monitored to inform decision on selection criteria and organizational focus.

The Criteria

Common financial criteria used in project selection include:

In addition to financial criteria, none financial criteria may be selected based on the nature of the organization’s activities. While organizations try to balance financial and none financial criteria, at times organizations my do projects that are losing money but have a strategic importance to the firm. Such criteria include:

The Selection Model

While project selection could be done using a single criterion, in most cases multiple criteria are used. Many organizations have to select from a list of projects that are complex, difficult to assess, and often noncomparable.

Most organizations need to start by bringing the number of projects under consideration down. This can be achieved using a threshold on a few single criteria, or using checklists and Q-sort method.

Some organizations use checklist models. These take the form of a list of questions which are used to assess potential projects and to determine their acceptance or rejection. These allow greater flexibility in selecting among many different types of projects and are easily used across different divisions and locations. However, they fail to answer the relative importance or value of a potential project to the organization and does not allow for comparison with other potential projects. They can be helpful as screening tools to narrow down the number of projects being considered.

Example:

Topic Question
Strategy/alignment What specific organization strategy does this project align with?
Driver What business problem does the project solve?
Sponsorship Who is the project sponsor?
Risk What is the impact of not doing this project?
Risk How risky is the project?
Benefits, value, ROI What is the value of the project to this organization?
Benefits, value, ROI When will the project show results?
Objectives What are the project objectives?
Organization culture Is our organizational culture right for this type of project?
Resources Will internal resources be available for this project?
Schedule How long will this project take?
Finance/portfolio What is the estimated cost of the project?
Portfolio How does this project interact with current projects?

Another method used is the Q-Sort method:

  1. Develop a set of statements or project descriptions for evaluation.
  2. Define the condition: For example, rank these projects from most to least important, or group these projects into high, medium and low priority.
  3. Administer the Q-sort to respondents: Each respondent is given a set of cards with the descriptions printed on them and is asked to sort them based on the condition.
  4. Calculate the correlation coefficients between each respondent’s sort and a “standard” sort
  5. Analyze the correlations to identify clusters of similar attitudes or perspectives, and facilitate a discussion to better understand opinions with the potential to reach a consensus

When a small enough number of projects are being considered, a weighted decision matrix is considered the best approach. This method can consider multiple financial and non-financial quantitative and qualitative criteria to create a composite score for the possible projects. Each criterion is weighted relative to its importance, allowing important factors to stand out.

Another approach is a scrub down, where a group of experts attempts to “murder” a project proposal by pointing out its flaws and weaknesses.

The organization may also decide to perform discovery-driven planning. In this approach, the project is not fully funded, but instead funds are assigned to determine if the initial assumptions were accurate. This will allow the organization to learn more about the project, rather than necessarily implement it.

Irrespective of which combination of these methods are used, in the end one has to assess whether the final selection makes strategic sense or not.

Why Projects Fail?

Summary

Practice

Bibliography