Many organizations improperly close their projects. As a result, they do not benefit from all the knowledge gained during the implementation of a project.
The PMI Perspective
The PMI describes the Project Closing Process Group as follows:
Information from team is gathered and organize into one central repository a close-out report that can be used by future projects. This includes:
Summary of the project and deliverables
Data on performance related to schedule, cost, and quality
Summary of the final product, service, or project and how it supports the organization’s business goals
Risks encountered and how they were mitigated
Lessons learned
Extraneous information is disposed
Contracts are closed with final payments made
Staff, equipment, and other resources are reassigned to other projects or operational units
Final project evaluation is performed to understand actual schedule, budget, scope, and lessons learned, and to assess:
Has the project been made obsolete or less valuable by technical advances and is continuation still cost-effective?
Is it time to integrate the project into regular operations?
Are there better alternative uses for the funds, time, and personnel devoted to the project?
Has the market or regulatory requirements, altered the need for the project’s output?
Celebrating success and team recognition
A major part of project closure is post project reviews. Purpose is to allow future projects to learn from past project experience. These reviews take the budget, facilities, tools and staff as their input. During the review, the following elements are assessed:
Purpose, Mission
Structure, Roles
Leadership
Relationship with staff and clients
Rewards
Systems and processes
The aim is to identify what worked and what did not work. and whether outcomes were aligned with purpose and mission. The outcome are improvements in how work is done, and in products and services.
Close-out Report (Template)
Project:[Project Title]
Project ID: [ID]
Project Manager: [Name]
Sponsor: [Name]
Date of close-out: [YYYY-MM-DD]
Executive Summary
[One-paragraph summary of outcomes vs objectives.]
Final Status of Deliverables-
[Deliverable 1 — Accepted / Rejected; Notes]
[Deliverable 2 — Accepted / Rejected; Notes]
Performance Summary
Schedule: Planned finish [date]; Actual finish [date]; Variance [days]
Cost: Budget [amount]; Actual cost [amount]; Variance [amount]
Scope: [Summary of scope changes and approvals]
Lessons Learned (Top 5)
1) [Lesson 1 — root cause and recommendation]
2) [Lesson 2]
3) [Lesson 3]
Outstanding Items and Follow-up Actions
[Item] — Owner — Due date
Contract and Procurement Closure
[Status of vendor contracts, final payments, warranties]
Knowledge Transfer and Handover
Handover package location: [repository link or path]
Training delivered: [dates, attendees]
Archive and Records
Location of archived documents: [path]
Retention period: [e.g., 7 years]
Formal Acceptance
Sponsor signature: [Name, Date]
Project Manager signature: [Name, Date]
Example: Valley College Online Registration System
Before closing the Online Course Registration project, the team:
Confirms that all deliverables are completed and accepted by the sponsor.
Ensures outstanding defects are either resolved or documented in a post‑release support plan.
Closes contracts and verifies all invoices are paid.
Releases team members back to their functional managers or new projects.
Conducts a lessons learned session and records outcomes in the organizational process assets.\
Here are some examples of lessons which may be documented:
Early engagement of front‑desk staff improved usability and reduced training time.
Integration risks were underestimated; future projects should allocate more time for technical prototyping and include specific integration risk triggers.
Contingency reserves for testing and training were sufficient, but developer time was underestimated.
Closing extends beyond project completion into benefits tracking and organizational learning. Six months after the registration system goes live, as part of the Benefit Realization Review:
The college measures registration wait times, error rates, and student satisfaction.
Actual benefits are compared against those anticipated in the business case.
Additional small enhancements are planned to close any gaps.
This will not only help assess the success of the project, but also may inform future projects.
Summary