Monitoring and controlling focuses on assessing whether the plan is being correctly implemented. While it can focus on many aspects of the work, we will focus on monitoring and control the work.
Learning Objectives
By the end of this unit, you should be able to:
Identify the four steps for controlling a project
Utilize a tracking Gantt to monitor time performance
Understand and appreciate the significance of earned value management
Calculate and interpret cost and schedule variance
Calculate and interpret performance and percent indexes
Forecast final project cost
The PMI Perspective
The PMI defines the Monitor and Control Project Work process as followed:
To monitor a project, we need to set up a project monitoring system:
Determine what data needs to be collect: Typically the goal of data collection is to help with trade-offs, the most common being in time, cost, scope and quality of the project. We need to identify concerns about resources, activities, scheduling, issues, and how successful the project is from the data. Money is often the basis of decision making, so being able to translate the data to dollar amounts is useful. The data need to answer questions such as:
What is the current status of the project in terms of schedule and cost?
How much will it cost to complete the project?
When will the project be completed?
Are there potential problems that need to be addressed now?
What, who, and where are the causes for cost or schedule overruns?
If there is a cost overrun midway in the project, can we forecast the overrun at completion?
Determine how, when, and who will collect the data: Questions to answer include:
Will the data be collected by the project team, contractor, independent cost engineers, project manager?
Will the data be derived electronically from some form of surrogate data?
Should the reporting period be one hour, one day, one week, or what?
Is there a central repository for the data collected and is someone responsible for its dissemination?
What should be in progress reports? (typical stricture is: progress since last report, current status of project: 1) schedule, 2) cost, 3) scope, cumulative trends, problems and issues since last report, actions and resolutions of earlier problems, new variances and problems identified, corrective action planned)
Who gets the progress reports? How will the reports be transmitted? When will the reports be distributed?
What should be in milestone reports? These reports are created when a major milestone is reached, with the goal of keeping everyone up-to-date on project status, and are the only reports some executives and clients may recieve.
Analyze the data: For example you may use earned value analysis to achieve this.
Report current progress
Proper monitoring will not only enable organizations to become better at project management (hence “winning” projects), it also allows them to learn from what they do. The key here is using the plan as the baseline: the reference used to assess performance.
The Project Control Process
Control is about taking corrective action based on the result of comparing actual performance against plan to identify deviations, and evaluate possible alternative courses of actions. Project control steps for measuring and evaluating project performance include:
Setting a baseline plan: This is the original plan created for the project and approved by the project sponsor.
Measuring progress and performance: Using the monitoring system outlined above
Comparing plan against actual: This can be achieved through various methods and indices.
Taking action: This can be making changes to the plan (for example performing schedule compression), or changing resource levels or scope.
Reviewing the project as it goes at each milestone and/or at each time point can determine if the project is running ahead or behind, and whether the costs are tracking as predicted.
Reports
Throughout the life of the project, various standard reports may be issued, including progress reports, milestone report, issues list, time/cost reports, etc. The team needs to decide during planning:
Who gets these reports?
How will the reports be transmitted?
When will the reports be distributed?
For example:
What Information
When?
Mode
Responsible
Recipient
Milestone report
Bimonthly
E-mail
Project office
Senior management
Time/cost report
Weekly
E-mail
Project office
Staff and customer
Risk report
Weekly
E-mail
Project office
Staff and customer
Issues
Weekly
E-mail
Anyone
Staff and customer
Team meeting times
Weekly
Meeting
Project manager
Staff and customer
Outsourcing performance
Bimonthly
Meeting
Project manager
Project office, staff, and customer
Change requests
Anytime
Document
Project manager, customer, design
Project office, staff, and customer
Stage gate decisions
Monthly
Meeting
Project office
Senior management
A progress reports may take this form:
Progress since last report
Current status of project: 1) schedule, 2) cost, 3) scope
Cumulative trends
Problems and issues since last report:
Actions and resolutions of earlier problems
New variances and problems identified
Corrective action planned
Organizations may alternatively use a live dashboard to communicate project status:
Example: Project Status Report
Project Information
Project: Conveyor belt upgrade (#S123)
Project Manager: Hendric Gould
Project Priority (Current): 3
Status Date: 1 May 2026
Earned Value Figures
PV
EV
AC
SV
CV
BAC
588,240
566,064
596,800
- 22,176
- 30,736
1,051,200
EAC
VAC
EAC
CPI
PCIB
PCIC
1,090,640
- 39,440
1,107,469
0.95
0.538
0.547
Project Description
A computer-controlled conveyor belt that will move and position items on the belt with accuracy of less than one millimeter.
Status Summary
The project is approximately 25 days behind schedule and $30,736 over budget.
Explanations
The schedule variance has moved from noncritical activities to those on the critical path.
Integration first phase, scheduled to start 3/26, is now expected to start 4/19, which means it is approximately 25 days behind schedule.
This delay is traced to the loss of the second design team, which made it impossible to start utilities documentation on 2/27 as planned.
The cost variance to date is largely due to a design change that cost $21,000.
Major Changes Since Last Report
The major change was the loss of one design team to the project.
Total Cost of Approved Design Changes
$21,000 — most of this amount is attributed to the improved design of the serial I/O drivers.
Projected Cost at Completion
EAC is estimated to be $1,107,469, representing an overrun of $56,269, given a CPI of 0.95.
Forecasted Completion Date
October 23
Risk Watch
Five team members were stricken with flu.
Project Dashboard
Project Information
Project Name:
High‑Level Description:
Executive Sponsor:
Project Manager (PM):
Start Date:
End Date:
Report Period:
Overall Status
Schedule:
Resources:
Budget:
Key Activities
Key Activities
Recent Accomplishments
Upcoming Key Deliverables
Status
Activity #1
🟡 Concern
Activity #2
🟢 On Track
Activity #3
🔴 Issue
Status Legend
🟢 On Track
🟣 Complete
🟡 Concern
🔴 Issue
🔵 On Hold
🔷 Canceled
⚪ Not Started
Current Key Risks
Threats and opportunities; mitigation strategies
Current Key Issues
Description of issues impacting the project
Monitoring Time Performance
Typical tools used for communicating project schedule status are:
Gantt chart (bar chart) which is the most favored, used, and understandable. It is commonly referred to as a tracking Gantt chart, showing current status against planned/baseline.
Control chart is used to plot the difference between the scheduled and actual times on the critical path at a given point on the project. This will allow to identify deviations and take action.
Milestone schedules are often used to keep more distant stakeholders informed on the progress of a project.
Time Variance is defined as: TV = ST – AT (ST: Schedule Time, AT: Actual Time). A negative variance indicates you are behind schedule. Alternatively, the Time Performance Index can be used: TPI = ST/AT (TPI<1 means you are behind schedule)
Monitoring Cost
Three cost values are tracked throughout the project:
Estimated cost is how much you calculated it will cost to do certain pieces of work (including the entire project) during planning
Budgeted cost is the amount you are allowed to spend. This usually includes contingencies.
Actual cost is the amount you do spend.
In most cases, costs are plotted on a cost-time graph. A simple measure of performance is how much your actual costs are over, or under the budgeted costs for the period. However, this is not meaningful without considering how much work you have completed.
For example, you might have planned to paint 5 rooms which you budgeted $5,000 for. Now, knowing you spend $6,000, it may be that:
You have painted 6 rooms instead of 5, so you are ahead of schedule.
You have painted 4 rooms in that time, so you are behind schedule and over budget.
You have pained 5 rooms, so you are on schedule and over budget.
Earned Value Management (EVM)
Looking at the schedule or cost alone does not provide a full picture:
You may be on schedule, but have spent more than you planned.
You may be under budget, but at the same time have not achieved as much as you planned.
We need a method that provides us insight on both at the same time.
In the 1960s, the U.S. Department of Defense (DoD) created Earned Value Management (EVM). This method combines scope (WBS), schedule (project network calculations), and resource measurement to assess project performance and progress.
To use this method, we need three pieces of information:
Planned Value (PV) also called budgeted cost of the work scheduled (BCWS) or planned cost of the work scheduled: The planned time-phased baseline of the value of the work scheduled or in other words, budget that has been approved for the work scheduled to be completed within a specific date. An approved cost estimate of the resources scheduled in a time-phased cumulative baseline. This shows the amount of commutative costs at each control point within the project, and is useful for progress reports and cash flow estimation.
Earned Value (EV) also called budgeted cost of the work performed (BCWP) or budgeted cost of the work completed: Earned value for a task is the budgeted value of the work accomplished. Work accomplished is often measured in terms of percentages (e.g., 25% complete) in which case, EV is simply percent complete times its original budget. . Some of the rules used to calculate EV for short-duration activities and/or small-cost activities include:
Ratio of cost (or time) expended to cost (or time) budgeted
0/100 rule: Assumes 100% of the budget is earned when the work package is completed
50/50 rule: Allows 50% of the value of the work package budget to be earned when it is started and 50% to be earned when the package is completed.
Percent complete with weighted monitoring gates: Uses subjective estimated percent complete in combination with hard, tangible monitoring points. (EV = % complete x budget)
Actual Cost (AC) also called actual cost of the work performed (ACWP) or actual cost of the work completed: Actual cost of the work completed. The sum of the costs incurred in accomplishing work.
With this information, two approaches can be used to assess the progress of the project:
Variances: A positive variance indicates a desirable condition, while a negative variance suggests problems or changes that have taken place.
Schedule variance (SV) is the difference between the earned value and the baseline to date where: SV = EV – PV (in percentage: SV% = SV / PV; Negative means behind schedule)
Cost variance (CV) is the difference between the earned value and the actual costs for the work completed to date where: CV = EV – AC (in percentage: CV% = CV / AC; negative means cost overrun)
Tells us if the work accomplished costs more or less than was planned at any point over the life of the project.
Indices: An index of less than one is not desirable.
Cost performance index (CPI)= EV / AC (Measures cost efficiency of the work accomplished to date)
Schedule performance index (SPI)= EV / PV (Measures scheduling efficiency to date)
Percent complete index budgeted costs (PCIB) = EV/BAC
Management reserve index (MRI) = CV / MR (Is popular in the construction industry; shows the amount of management reserves that has been absorbed by cost overruns)
Cost Schedule Index CSI = EV^2/(AC)(PV)
We can also use this information to estimate the cost of the project at completion: EAC = ETC + AC
where EAC is estimated cost at completion and ETC is estimated cost to complete remaining work calculated through various methods including: ETC = (BAC – EV) / CPI
where BAC is budget at completion (The total budgeted cost of the baseline or project cost accounts). This allows us to calculate three additional measures:
Percent complete index actual costs (PCIC) = AC/EAC
To Complete Performance Index (TCPI) = (BAC - EV)/(BAC - AC) (Measures the amount of value each remaining dollar in the budget must earn to stay within the budget, with a ratio less than 1 indicating an ability to complete the project without using all of the remaining budget).
Variance at completion (VAC) = BAC – EAC indicates expected actual over- or under-run cost at completion.
Common Issues
The indices and variances allow us to identify that there is an issue, but we need further analysis to identify the root causes.
Cost overruns are typically the result of:
Poor estimating and unrealistic budget: you need to resolve this for future projects. For the current project, you can estimate again and see what your options are.
Failure to understand client requirement: you need to resolve this for future projects. For the current project, you can try to understand these better.
Accepting client requests without management approval or formal change control: create a formal change management process.Scope creep causes problems because the “minor refinements” eventually build to be major scope changes and you need to properly vet them. Baseline changes should be allowed only if it is clear that the project will fail without the change, the project will be improved significantly with the change, or the customer wants it and will pay for it.
Lack of management policy on reporting
Unforeseen technical problems or realization of risks
Schedule delays: Solutions here include identifying and solving specific problems (for example issues with people, tasks or other bottlenecks), use schedule compression, change scope of the project, do nothing or abort the project.
The key when faced with any issue above is to take action and fast. As you progress through the project, making sequential decisions, you become constrained by your previous decisions and you lose the flexibility you originally had in decision making. Projects may implement go-no-go points controls (a predetermined standard must be met for permission to be granted to continue). Standard reviews and decision gates to ensure regular monitoring and control.
Even when a decision is conceptualized, the PM must look at how it affects the triple constraint (time, cost, scope) and how it impacts project quality. They then need to submit a change control for review and approval to ensure the change and its impacts are evaluated and relevant documents (including the project plan) are updated.
Earned Value Management Example 1
A project has a Budget at Completion (BAC) of $200,000. At the end of month 3 the planned value, earned value, and actual cost are:
Planned Value (PV) = $75,000
80% of the planned work is complete -> Earned Value (EV) = 0.8 x $75,000 = $60,000
Cost Variance (CV) = EV − AC = 60,000 − 70,000 = −10,000 < 0
So the project is overbudget and behind schedule. We would have the same conclusion with the indices:
Schedule Performance Index (SPI) = EV / PV = 60,000 / 75,000 = 0.80 < 1
Cost Performance Index (CPI) = EV / AC = 60,000 / 70,000 ≈ 0.857 < 1
CV = −$10,000 and CPI ≈ 0.857 indicate cost inefficiency (spending more than the value earned).
With this knowledge we can estimate the expected cost of the project, if things do not improve: Estimate at Completion EAC = BAC / CPI = 200,000 / 0.857 ≈ 233,333
EAC ≈ $233,333 suggests the project will exceed the original budget by about $33,333 if current cost performance continues.
EVM Example 2
Suppose a four‑month project has a total budget at completion (BAC) of CAD 100,000. The planned spending and actual progress at the end of Month 2 are as follows:
Plan: Spend CAD 25,000 in Month 1 and CAD 25,000 in Month 2. By end of Month 2, the planned cumulative PV = 25,000 + 25,000 = CAD 50,000.
Earned Value (EV)- The work planned for the first two months represents 50% of the total project scope. At the end of Month 2, only 40% of the total scope has actually been completed. EV = 40% of BAC = 0.40 × 100,000 = CAD 40,000.
Actual Cost (AC)- Actual spending by end of Month 2 is CAD 55,000.
Interpretation: Expected overrun at completion is roughly CAD 37,000.
You can then connect these metrics back to your control steps: identify root causes (e.g., underestimated tasks, resource issues), consider schedule compression, scope adjustments, or resource changes, and raise a formal change request if necessary.
EVM Example 3
A software development project has a total budget of $100,000 and is scheduled to be completed in 10 weeks. The progress is being monitored at the end of week 6.
At this point, the project manager reports the following:
The actual cost (AC) incurred is $65,000.
The team has completed 60% of the total project work.
Assuming a linear rate of progress and expenditure, analyze the project’s performance using EVM metrics and answer the following questions:
What is the project’s Planned Value (PV)?
What is the project’s Earned Value (EV)?
What is the Cost Variance (CV) and Cost Performance Index (CPI)? Is the project over or under budget?
What is the Schedule Variance (SV) and Schedule Performance Index (SPI)? Is the project ahead or behind schedule?
What is the Estimate at Completion (EAC) based on the current CPI?
What is the Variance at Completion (VAC)?
To solve this problem, we will first calculate the foundational EVM values and then use them to determine the project’s variance and performance indexes.
Given data:
Total Budget (Budget at Completion, BAC): $100,000
Planned Duration: 10 weeks
Status Date: End of Week 6
Actual Cost (AC): $65,000
Percent Complete (Actual): 60%
Planned Value (PV)
PV is the budgeted cost of work that was planned to be completed by the status date. Since the project is 6 weeks into a 10-week schedule, the planned percentage of completion is 6/10=60%
Analysis: The CPI of 0.92 means that for every dollar spent, the project is only earning 92 cents of value. A CPI less than 1.0 indicates a cost overrun.
Schedule Variance (SV) and Schedule Performance Index (SPI)
SV and SPI measure the project’s schedule efficiency.
Analysis: The SV of $0 indicates the project is exactly on schedule. The value of the work completed matches the value of the work that was planned to be completed by this date.
Analysis: The SPI of 1.0 confirms that the project is right on schedule.
Estimate at Completion (EAC)
EAC is the projected final cost of the project based on current performance. Assuming the current cost performance will continue, we can use the formula:
𝐸𝐴𝐶 = 𝐵𝐴𝐶 / 𝐶𝑃𝐼 = $100,000 / 0.92 ≈ $108,696
Analysis: Due to the current cost performance, the project is now forecasted to cost $108,696 to complete, which is over the original $100,000 budget.
Variance at Completion (VAC)
VAC is the difference between the original budget and the new estimate for the final cost.
𝑉𝐴𝐶 = 𝐵𝐴𝐶 − 𝐸𝐴𝐶 = $100,000 − $108,696 = −$8,696
Analysis: The negative VAC indicates that the project is forecasted to have a budget deficit of approximately $8,696 upon completion.
Outcomes of Monitoring and Controlling
Through Monitoring and Controlling, you gain:
A reliable understanding of the status of the project
Actionable data to facilitate decision making
Timely and appropriate actions to keep project performance on track
Achieving targets and generating business value by making informed and timely decisions based on reliable forecasts and evaluations
The aim is to avoid cost overruns by resolving issues early. Cost overruns can be due to:
Poor estimating, unrealistic budget
Failure to understand client requirement
Accepting client requests without management approval
Unforeseen technical problems
Schedule delays
As you progress through the project, making sequential decisions, you become constrained by your previous decisions and flexibility decreases. Care must be taken at the start to preserve as much flexibility as possible.
Control
Control is about taking actions based on the information gathered from monitoring. To make a change the PM must look at how it affects the triple constraint (time, cost, scope) and how it impacts project quality, before a decision can be made. In many cases, major changes may require sponsor approval.
Options include:
Go/no-go controls: A predetermined standard must be met for permission to be granted to continue project work
Changing the schedule or budget based on the actual performance
Changing the project pace or compressing the schedule
Scope changes (which will follow the change request process)
After a control decision is made, impact needs to be documents and relevant documents updated. The organization will monitor performance post control to assess the actual outcome which will allow future projects to learn from past project experience.