Monitoring and Controlling

Monitoring and controlling focuses on assessing whether the plan is being correctly implemented. While it can focus on many aspects of the work, we will focus on monitoring and control the work.

Learning Objectives

By the end of this unit, you should be able to:

The PMI Perspective

The PMI defines the Monitor and Control Project Work process as followed:

Creating a Project Monitoring Information System

To monitor a project, we need to set up a project monitoring system:

The Project Control Process

Control is about taking corrective action based on the result of comparing actual performance against plan to identify deviations, and evaluate possible alternative courses of actions. Project control steps for measuring and evaluating project performance include:

  1. Setting a baseline plan: This is the original plan created for the project and approved by the project sponsor.
  2. Measuring progress and performance: Using the monitoring system outlined above
  3. Comparing plan against actual: This can be achieved through various methods and indices.
  4. Taking action: This can be making changes to the plan (for example performing schedule compression), or changing resource levels or scope. Reviewing the project as it goes at each milestone and/or at each time point can determine if the project is running ahead or behind, and whether the costs are tracking as predicted.

Reports

Throughout the life of the project, various standard reports may be issued, including progress reports, milestone report, issues list, time/cost reports, etc. The team needs to decide during planning:

For example:

What Information When? Mode Responsible Recipient
Milestone report Bimonthly E-mail Project office Senior management
Time/cost report Weekly E-mail Project office Staff and customer
Risk report Weekly E-mail Project office Staff and customer
Issues Weekly E-mail Anyone Staff and customer
Team meeting times Weekly Meeting Project manager Staff and customer
Outsourcing performance Bimonthly Meeting Project manager Project office, staff, and customer
Change requests Anytime Document Project manager, customer, design Project office, staff, and customer
Stage gate decisions Monthly Meeting Project office Senior management

A progress reports may take this form:

Organizations may alternatively use a live dashboard to communicate project status:

Example: Project Status Report

Project Information
Earned Value Figures
PV EV AC SV CV BAC
588,240 566,064 596,800 - 22,176 - 30,736 1,051,200
EAC VAC EAC CPI PCIB PCIC
1,090,640 - 39,440 1,107,469 0.95 0.538 0.547
Project Description

A computer-controlled conveyor belt that will move and position items on the belt with accuracy of less than one millimeter.

Status Summary

The project is approximately 25 days behind schedule and $30,736 over budget.

Explanations

The schedule variance has moved from noncritical activities to those on the critical path.
Integration first phase, scheduled to start 3/26, is now expected to start 4/19, which means it is approximately 25 days behind schedule.
This delay is traced to the loss of the second design team, which made it impossible to start utilities documentation on 2/27 as planned.
The cost variance to date is largely due to a design change that cost $21,000.

Major Changes Since Last Report

The major change was the loss of one design team to the project.

Total Cost of Approved Design Changes

$21,000 — most of this amount is attributed to the improved design of the serial I/O drivers.

Projected Cost at Completion

EAC is estimated to be $1,107,469, representing an overrun of $56,269, given a CPI of 0.95.

Forecasted Completion Date

October 23

Risk Watch

Five team members were stricken with flu.

Project Dashboard

Project Information
Overall Status
Key Activities
Key Activities Recent Accomplishments Upcoming Key Deliverables Status
Activity #1     🟡 Concern
Activity #2     🟢 On Track
Activity #3     🔴 Issue
Status Legend
Current Key Risks

Threats and opportunities; mitigation strategies

Current Key Issues

Description of issues impacting the project

Monitoring Time Performance

Typical tools used for communicating project schedule status are:

Time Variamce.png

Monitoring Cost

Three cost values are tracked throughout the project:

5aef976f181c48ce19dac1f66f59ea95.png

Earned Value Management (EVM)

Looking at the schedule or cost alone does not provide a full picture:

In the 1960s, the U.S. Department of Defense (DoD) created Earned Value Management (EVM). This method combines scope (WBS), schedule (project network calculations), and resource measurement to assess project performance and progress.

To use this method, we need three pieces of information:

With this information, two approaches can be used to assess the progress of the project:

We can also use this information to estimate the cost of the project at completion: EAC = ETC + AC where EAC is estimated cost at completion and ETC is estimated cost to complete remaining work calculated through various methods including: ETC = (BAC – EV) / CPI where BAC is budget at completion (The total budgeted cost of the baseline or project cost accounts). This allows us to calculate three additional measures:

Common Issues

The indices and variances allow us to identify that there is an issue, but we need further analysis to identify the root causes. Cost overruns are typically the result of:

The key when faced with any issue above is to take action and fast. As you progress through the project, making sequential decisions, you become constrained by your previous decisions and you lose the flexibility you originally had in decision making. Projects may implement go-no-go points controls (a predetermined standard must be met for permission to be granted to continue). Standard reviews and decision gates to ensure regular monitoring and control.

Even when a decision is conceptualized, the PM must look at how it affects the triple constraint (time, cost, scope) and how it impacts project quality. They then need to submit a change control for review and approval to ensure the change and its impacts are evaluated and relevant documents (including the project plan) are updated.

Earned Value Management Example 1

A project has a Budget at Completion (BAC) of $200,000. At the end of month 3 the planned value, earned value, and actual cost are:

From here, we can calculate:

So the project is overbudget and behind schedule. We would have the same conclusion with the indices:

CV = −$10,000 and CPI ≈ 0.857 indicate cost inefficiency (spending more than the value earned).

With this knowledge we can estimate the expected cost of the project, if things do not improve: Estimate at Completion EAC = BAC / CPI = 200,000 / 0.857 ≈ 233,333

EAC ≈ $233,333 suggests the project will exceed the original budget by about $33,333 if current cost performance continues.

EVM Example 2

Suppose a four‑month project has a total budget at completion (BAC) of CAD 100,000. The planned spending and actual progress at the end of Month 2 are as follows:

Now compute variances and performance indices.

You can then connect these metrics back to your control steps: identify root causes (e.g., underestimated tasks, resource issues), consider schedule compression, scope adjustments, or resource changes, and raise a formal change request if necessary.

EVM Example 3

A software development project has a total budget of $100,000 and is scheduled to be completed in 10 weeks. The progress is being monitored at the end of week 6. 

At this point, the project manager reports the following: 

Assuming a linear rate of progress and expenditure, analyze the project’s performance using EVM metrics and answer the following questions:

  1. What is the project’s Planned Value (PV)?
  2. What is the project’s Earned Value (EV)?
  3. What is the Cost Variance (CV) and Cost Performance Index (CPI)? Is the project over or under budget?
  4. What is the Schedule Variance (SV) and Schedule Performance Index (SPI)? Is the project ahead or behind schedule?
  5. What is the Estimate at Completion (EAC) based on the current CPI?
  6. What is the Variance at Completion (VAC)? 

To solve this problem, we will first calculate the foundational EVM values and then use them to determine the project’s variance and performance indexes. 

Given data: 

  1. Planned Value (PV)

PV is the budgeted cost of work that was planned to be completed by the status date.  Since the project is 6 weeks into a 10-week schedule, the planned percentage of completion is 6/10=60%

𝑃𝑉 = Planned Percentage of Completion × BAC = 60% × $100,000 = $60,000

  1. Earned Value (EV) 

EV is the value of the work actually completed by the status date. 

𝐸𝑉 = Actual Percentage of Completion × BAC = 60% × $100,000 = $60,000

  1. Cost Variance (CV) and Cost Performance Index (CPI) 

CV and CPI measure the project’s cost efficiency. 

Cost Variance (CV): 𝐶𝑉 = 𝐸𝑉 − 𝐴𝐶 = $60,000 − $65,000 = −$5,000

Cost Performance Index (CPI): 𝐶𝑃𝐼 = 𝐸𝑉 / 𝐴𝐶 = $60,000 / $65,000 ≈ 0.92

  1. Schedule Variance (SV) and Schedule Performance Index (SPI) 

SV and SPI measure the project’s schedule efficiency. 

Schedule Variance (SV):  𝑆𝑉 = 𝐸𝑉 − 𝑃𝑉 = $60,000 − $60,000 = $0

Schedule Performance Index (SPI): 𝑆𝑃𝐼 = 𝐸𝑉 / 𝑃𝑉 = $60,000 / $60,000 = 1.0

  1. Estimate at Completion (EAC) 

EAC is the projected final cost of the project based on current performance. Assuming the current cost performance will continue, we can use the formula:  𝐸𝐴𝐶 = 𝐵𝐴𝐶 / 𝐶𝑃𝐼 = $100,000 / 0.92 ≈ $108,696

  1. Variance at Completion (VAC) 

VAC is the difference between the original budget and the new estimate for the final cost.  𝑉𝐴𝐶 = 𝐵𝐴𝐶 − 𝐸𝐴𝐶 = $100,000 − $108,696 = −$8,696

Outcomes of Monitoring and Controlling

Through Monitoring and Controlling, you gain:

The aim is to avoid cost overruns by resolving issues early. Cost overruns can be due to:

As you progress through the project, making sequential decisions, you become constrained by your previous decisions and flexibility decreases. Care must be taken at the start to preserve as much flexibility as possible.

risk-change-flexibility.png

Control

Control is about taking actions based on the information gathered from monitoring. To make a change the PM must look at how it affects the triple constraint (time, cost, scope) and how it impacts project quality, before a decision can be made. In many cases, major changes may require sponsor approval.

Options include:

After a control decision is made, impact needs to be documents and relevant documents updated. The organization will monitor performance post control to assess the actual outcome which will allow future projects to learn from past project experience.

Summary

Practice

  1. Earned value analysis explained for project management
  2. Cost Performance Index (CPI) and Cost Variance (CV) explained
  3. Schedule Performance Index (SPI) and Schedule Variance (SV) explained
  4. Earned value analysis worked example
  5. How to interpret an earned value graph
  6. Earned Value Example