Adjusting the Schedule

Learning Objectives

By the end of this unit, you should be able to:

Project Pace

Some organizations define standard paces for their projects. Depending on the situation (being behind schedule or strategic priority), the pace assigned to the project may change. This essentially means a compromise on quality of work or some other aspect of the project in order to deliver the project on time. As an example:

Category Normal Rush Blitz
Approved Project Definition Fully developed and approved before work begins Approved quickly; some details may be incomplete Minimal definition; approval may occur after work starts
Study of Alternates Thorough study of alternatives Limited study of alternatives No study of alternatives
Engineering Design Complete design before field work starts Partial design; overlaps with field work Minimal design; field work begins immediately
Issue Engineering to Field Adequate planning time; typically 1½–2 months lead time Little or no lead time No lead time
Purchasing Normal purchasing cycles Accelerated purchasing Emergency purchasing
Premium Payments None Some premium payments Extensive premium payments
Field Crew Strength Normal crew size Increased crew size Maximum crew size
Probable Cost Baseline cost Higher cost Highest cost
Difference Compared with Normal Pace — Design & Development Baseline effort Increased effort Maximum effort
Difference Compared with Normal Pace — Engineering & Construction Costs Baseline cost Higher cost Highest cost
Probable Time Longest duration Shorter duration Shortest duration

Hammock Activity

Some, often unrelated group of activities (for example monitoring a specific work and controlling it, or overhead functions like project management itself, site liaison, invoicing, and the management of equipment requirements) “hang” between two defined points in a project schedule, rather than having their own distinct start and finish dates. These are called Hammock activities. Their duration is determined after the network plan is drawn.

Schedule Compression

Sometimes when planning a project, your network leads to a timeline which is not compatible with the original end date or milestones set for the project. This may also happen during the implementation of the project, where the project due dates turn out to be unrealistic (tasks falling behind), there are changes in the project scope (requiring replanning), or key resources and data become unavailable. At this point, the schedule would need to be adjusted.

Before the project starts, we can ensure our plan is realistic and requires less rework by using multipoint estimation, including proper time buffers for work packages and the project as a whole, and ordering long-lead items early. Monitoring key activities is also a good preventative measure.

There are some simple solutions which could be considered first:

Overall, when faced with a situation where the timeline is no longer feasible, you need to focus on critical path, use the buggers, pull resources from less critical work to work on critical activities, move unused buffers to critical activities, run activities in parallel or during weekends, pressure team to work faster, get additional resources, or reduce scope. Two very common schedule compression methods are:

Other options when resources are constrained include reducing project scope or compromising quality.

5b03a6f076efd7633eec259b04fd5364.png Source: Project Management Institute. (2022). Process Groups: A Practice Guide. Newtown Square, Pennsylvania: Project Management Institute.

Crashing a Project

Crash is a term that has emerged in the project management lexicon for shortening the duration of an activity or a project beyond when it normally can be done. Crashing is used when there are time-to-market pressures, unforeseen delays, incentives (bonuses for early completion), contract commitments, pressure to reassign resources to other projects or high overhead costs.

The idea behind crashing is leveraging the interrelationship between time and cost: The faster an activity is completed, the more is the cost directly. Thus many activities can be sped up by spending more money. Of course, the resources to do this must be available. Sometimes the increase cost goes towards new technology (for example a machine to dig). Crashing affects everyone: If you have subcontractors, their schedules will also change. There are also tasks that inherently cannot be crashed: for example, if you need a regulator to approve something, that timeline is out of your hands.

There are situations were crashing makes sense. For example, some projects have penalty clauses that make the parent organization liable for late delivery—and sometimes bonuses for early delivery. Or the reduction in indirect costs may be enough.

To crash a project, we focus on the cost for crashing:

  1. Start with the normal schedule
  2. Select activities to crash, one at a time: First focus on the critical path(s), and then on whatever activity is least expensive to crash. Each activity has a crash slope defined as =”Crash cost - Normal cost” /”Crash time - Normal time” (assuming cost-time relationship is linear)
  3. Construct a project cost-duration graph: The project cost-duration graph is used to compare additional cost alternatives for benefits. You need to calculate the total cost (direct cost + indirect cost) of the project after crashing each activity. Your aim is to find the minimum of the curve, or a situation where the gain in time makes sense based on the additional costs. We assume here that normal time assumes low-cost, efficient methods to complete the activity, and crash time represents a limit—the greatest time reduction possible under realistic conditions. All accelerations occur within the normal and crash times.

Should You Crash?

Example: Fast Tracking

Let’s consider Valley College implementing a new online course registration system. Design and build phases may have been originally planned as sequential. To compress schedule, the team:

Example: Crashing

A project manager for a software development company has collected the following information about a new product launch. The activities, their predecessors, and cost data are listed in the table below. The company initially wants to find the cheapest way to reduce the project duration by just 3 weeks. Indirect costs are $300 per week. 

           
Activity  Predecessors Normal Time (Weeks) Normal Cost ($) Crash Time (Weeks) Crash Cost ($)
A – 5 10,000 4 12,000
B A 4 8,000 3 9,500
C A 7 15,000 5 18,000
D B, C 6 9,000 4 12,000
E B, C 8 18,000 6 21,000
F D 5 7,000 3 10,000
G E 6 12,000 4 14,000
H F, G 3 5,000 2 6,000

Your tasks:

  1. **Determine the critical path and normal project duration.
  2. Calculate the crash cost per week for each activity.
  3. Perform the crashing process one week at a time until the project duration is reduced by 3 weeks.
    • State which activity you crash in each step and why.
    • Show the new critical path(s) and duration after each crash. Calculate the total project cost after the 3-week crash. 

Solution 

1. Critical path and normal project duration 

a. Calculate Path Durations 

 b. Determine Critical Path and Normal Project Duration
The critical path is the longest path, which is A-C-E-G-H, with a normal duration of 29 weeks. 

2. Calculate crash cost per week 

3. Step-by-step crashing (3 weeks) 

Initial State: 

Crash Step 1: Reduce project by 1 week (to 28 weeks) 

Crash Step 2: Reduce project by 1 more week (to 27 weeks) 

Crash Step 3: Reduce project by 1 more week (to 26 weeks) 

4. Final project cost after 3-week crash 

a. Calculate the cost of crashing 

b. Calculate the new total project cost 

New Total Project Cost: $87,000 + $7,800 = $94,800

What If Cost, Not Time, Is the Issue?

In these situations, you have to cut costs by reducing project scope, asking the sponsor to take on more responsibility, outsourcing project activities or even the entire project or looking at workpackage level cost saving options.

Indicators of a Good Schedule

Probabilistic Methods

To this point we assumed point estimates for all items (time, cost, etc), but we know that in reality a range of points are possible. PERT—Program Evaluation and Review Technique is a method that takes into account the probability of our estimates in the calculations. This method assumes each activity duration has a range that statistically follows a beta distribution, and uses three time estimates for each activity: optimistic, pessimistic, and a most likely time estimate to represent activity durations. From these three time estimates, a weighted average estimate and a variance is calculated:

Estimate: \(t_e = \frac{o+4m+p}{6}\) (o: optimistic, m: most-likely, b: pessimistic)

Variance for activity: \(σ_{t_e} = \frac{p-o}{6}\)

Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations. The longer the project duration is, the higher is the probability of meeting that duration.

Variance for project \(σ_{T_E}= \sqrt{\sum{σ_{t_e}^2}}\)

From here we can calculate the z-value (a statistical factor) which tells the probability of completing the project in the time specified: \(Z = \frac{T_S - T_E}{σ_{T_E}}\)

where T_E = critical path duration, T_S = scheduled project duration, Z = probability (of meeting scheduled duration). This process assumes activities are statistically independent.

Nowadays most of this can be calculated using simulations in project management software, which provide insight into the range and distribution of project completion times and costs. This allows us to understand both time and budget uncertainty.