Risk

Learning Objectives

By the end of this unit, you should be able to:

What is Risk?

Risk is an uncertain event or condition that, if it occurs, can have a positive or negative impact on a project objective.

No amount of planning can overcome or control all risks. What we can do, is plan for them. The most important risk management tool is your own ability to learn about the project. The more you know about a project, the better you will foresee the many ways the project could go wrong and what the consequences will be if they do, and the better you will be at responding to these unexpected challenges.

Risk can also be mathematically defined, one definition being: Risk = Probability x Impact If we can somehow assess the probability of a risk, and its impact (in $s), we can assign a value to each risk, which will allow us to calculate things like contingency funds. Let’s say you have bought a part for $1,000 and you know there is a 1 in 100 chance that that part fails based on past experience. Then the risk here is equivalent to $1,000 x 1 / 100 = $10. This quantitative approach allows us to quantitatively assess the commulative risk of the project, which is the sum of all the small risks you identify.

4928a6dcabce3a02e802b4760c27f665.png

Acceptability of Risk

There is always risk! Whether the risk is acceptable or not depends on stakeholders or project sponsor and their

Other factors that affect whether one would accept a risk or not include:

Components of Risks

Each risk has a series of components:

Sources of Risk

Risks can be associated with the following elements:

Some of the common risk categories used include:

Risk Process Groups

PMI defines a particular set of processes when it comes to risk management. These are outlined in this section.

Planning Process Group

Plan Risk Management Process

This process focuses on setting up the approach and definitions for risk management.

Here you should start with existing information.

The Risk Management Plan itself should outline:

Identify Risks

Perform Qualitative Risk Analysis

Perform Quantitative Risk Analysis

Plan Risk Response

Implement risk response process (during execution)

Monitor Risks (during monitoring and controlling)

Risk Management

Risk management is an attempt to recognize and manage potential and unforeseen trouble spots that may occur when the project is implemented. Your aim is to identify:

By proper implementation of risk management, we will:

The risk management cycle follows these processes:

  1. Risk Planning: Define scope, team and strategy
  2. Risk Identification: Identify risk event, its impact and the likelihood of the event
  3. Risk Analysis: Use qualitative (ex. risk matrix) and quantitative (ex. Monte Carlo) methods to better understand the risks and their impact (on cost, schedule, technical performance, capability or functionality)
  4. Risk Response Planning: Create an action plan to mitigate the effects of the risk if possible, assign a resolution date and assign the risk to an owner
  5. Risk Monitoring and Control: Reassess the situation at regular intervals (weekly, monthly, quarterly) to identify new risks and update response plans

Risk Identification

The goal of risk identification is to generate a list of all the possible uncertain events that could affect the project. Of course, project objectives are themselves uncertain, but here our aim is to identify events that can product consequences (positive or negative) with respect to achieving project objectives.

Some of the common methods to identify risks are:

Example Risk Breakdown Structure bb3b30c84f1e4160155cee201c2845e5.png Example risk checklist:

After a risk is identified, a risk statement should be developed to describe the event and its effect:

Risk Assessment

After risks are identified, we need to analyze them to decide which one have higher priority than others. Usually this is done in two steps.

First, qualitative risk analysis is performed. Here the goal is to use experience to prioritize the list of risks and identify ones which may be worthy of further analysis. Usually this is done through a risk matrix, focused on probability of a risk and its impact (sometimes also the detection difficulty). To perform this qualitative assessment, we need to define the subjective scales for levels of probability and impact. Risks with high probability and impact are the most important to focus on, while as the combination of probability and impact is lowered, the risk becomes less important.

Second, we have quantitative risk assessment. Generally, the value of a risk in $ amounts can be defines as: Risk Value = Impact x Probability x Detection

Using probability analysis, statistical techniques, decision trees, net present value (NPV), or program evaluation and review technique (PERT) we can use this formula to assign a dollar amount to each risk, and compare them in terms of one factor. By adding the value of all risks we get to the total financial risk of the project.

Qualitative Risk Assessment

In this approach we first need to define a scales for probability and impact. For example, a probability scale may look like this:

Level Prob. Probability of Occurrence
1 0.1 You would be surprised if this happened.
2 0.3 Less likely to happen than not.
3 0.5 Just as likely to happen as not.
4 0.7 More likely to happen than not.
5 0.9 You would be surprised if this did not happen.

Or this:

Level Probability of Occurrence (%) Impact of Occurrence
High 41–50 Likely to occur. Has occurred in past projects.
Medium 31–40 Possible to occur.
Low 10–30 Unlikely to occur.

An impact scale may look like this:

Project Objective 1 Very Low 2 Low 3 Moderate 4 High 5 Very High
Cost Insignificant cost increase < 10% cost increase 10–20% cost increase 20–40% cost increase > 40% cost increase
Time Insignificant time increase < 5% time increase 5–10% time increase 10–20% time increase > 20% time increase
Scope Scope decrease barely noticeable Minor areas of scope affected Major areas of scope affected Scope reduction unacceptable to sponsor Project end item is effectively useless
Quality Quality degradation barely noticeable Only very demanding applications are affected Quality reduction requires sponsor approval Quality reduction unacceptable to sponsor Project end item is effectively useless

Or this:

Project Objective 1 Very Low 2 Low 3 Medium 4 High 5 Very High
Cost Insignificant cost increase < 5% cost increase 5–10% cost increase 10–20% cost increase > 20% cost increase
Schedule Insignificant schedule slippage Overall project slippage < 5% Overall project slippage 5–10% Overall project slippage 10–20% Overall project slippage > 20%
Functionality Functionality decrease barely noticeable Minor areas of functionality affected Major areas of functionality affected Functionality reduction unacceptable to client Project end item is effectively useless
Quality Quality degradation barely noticeable Only very demanding applications affected Quality reduction requires client approval Quality reduction unacceptable to client Project end item is effectively useless

You would then rate each risk on these scales. This will essentially help you identify the severity of the risks, something we can visualize in a risk matrix:

1beda9f5edf1e4598754cf6c97b85736.png The result of this analysis may look like this:

Risk Category Event Description Probability Criteria Prob. Score Impact Criteria Impact Score PI Score
Scope The scope of the project might change - Product scope well defined, only minor changes expected (Low)
- Product scope somewhat defined at a high level, a few changes expected (Med)
- Product scope very vague, large changes expected (High)
3 - Minor changes added via change control (Low)
- Moderate changes added with some difficulty (Med)
- Major changes added with severe impact to other requirements (High)
2 6
Scope Other projects may be added that depend on this project’s scope/work product - No overlap in scope with other projects (Low)
- Possible overlap in scope (Med)
- Overlap in scope with other projects (High)
1 - Other projects will not affect this project’s scope (Low)
- May require some cross-project coordination (Med)
- May require detailed cross-project coordination (High)
1 1
Team Team members may leave the project - Staff attrition < 20% (Low)
- Staff attrition 20–40% (Med)
- Staff attrition > 40% (High)
1 - Team is cross-trained and ready for attrition (Low)
- Key members can be replaced with lead time (Med)
- Some key members have unique skills no one else can perform (High)
2 2

Source: Introduction to Risk Assessment in Project Management (projectmanagementacademy.net)

Quantitative Risk Assessment Example

Let’s consider the case of Valley College’s project to develop a new student course registration system. To integrate this system into their existing student information system (SIS), the project team has to options:

To quantitatively assess these options taking into account the risk, we can calculate the expected monetary value (EMV):

Option 1 is cheaper in expectation but carries higher risk; Option 2 costs more but reduces risk. Decision‑makers compare EMV alongside risk appetite, strategic factors (e.g., vendor lock‑in), and schedule impacts.

Risk Response Options

Now that we have identified the most important risks, we can decide what to do with them.

Our options for threats include:

For opportunities, we have the option to:

Finally, we have two other options:

Which option you chose depends on various factors, including:

When a decision has been made on how to respond to the risks, we can document it in a Risk Response Matrix, which includes:

You can create a mitigated risk matrix showing the impact of risk responses.

Example: Risk Responses in Painting

Let’s assume we are painting a room. Before paint can be applied, the surface must be cleaned. Toxic chemicals are one method of cleaning. Risk: someone may injure their skin or their eyes due to a spill or splash of the chemical

Options:

In the real-world, you would use multiple responses. So you may get that insurance, require protective equipment, and make sure there is an eyewash station if you cannot use a different cleaner.

Contingency planning

A contingency plan is a predetermined response plan that is activated if a possible foreseen risk event becomes a reality. This is not part of the initial implementation and only goes into effect after risk or its trigger are recognized, with the goal of reducing or mitigating the negative impact of risk. A contingency plan is created as decision making under the risk condition may be delayed, there may be panic. and bad decisions may be made owing the the pressure. By planning ahead, you ensure better decisions are made.

Some examples of contingencies may include:

In terms of scheduling and costing, we have:

Examples of contingencies:

Risk and Contracts

For every element of the project, a project manager needs to make a “Make-or-Buy Analysis” to decide which work is done in house and which is done out of the organization. This decision is made based on: How much does it cost to build it as opposed to buying it? How will this decision affect the scope of your project? How will it affect the project schedule? Do you have time to do the work and still meet your commitments?

There are three main forms of contracts used to buy products, and outsource risks:

Putting it all together: Risk Register

The risk register is a documentation of all all identified risks, including descriptions, category, probability of occurring, impact, responses, contingency plans, owners, and current status. It includes:

As time passes, some risks are no longer uncertain. Residual risks are those that remain. Secondary risks are those that arise as a result of our risk responses.

A project manager may elicit risks from team members using a form like this: b5cab5200058f9cb490e6d1d5c741607.png A risk register may look like this:

Sr No Date Raised Risk Description Likelihood Impact Severity Owner Mitigating Action Contingency Plan Progress on Action Status Resource
1 20 Dec 2021 Project Sprints stories are not well defined High High High Product Owner Complete the Project Charter with full business cases and ensure requirements are gathered properly Escalate to project board Project Charter should be rewritten with full business case and requirements Open Project Charter Template
2 22 Dec 2021 Project design and deliverables/milestones are incomplete High High High Product Owner Define scope and deliverables in detail or seek expert help Assumptions and constraints defined; remove high‑risk items Workshops scheduled for training on deliverables and milestones In Progress Assumptions Log
3 23 Dec 2021 Non‑Competent Resources Medium Medium Medium Project Manager Schedule training or coaching from experts Escalate to project sponsor Sponsor agrees to hold briefing and arrange new resources In Progress Resource Planning Sheet
4 24 Dec 2021 Delays in appointing Expert Consultant or Freelancer Low Low Low Project Manager Communicate schedule early; check in with consultants regularly Escalate to project sponsor Build lead time into project schedule for onboarding delays Open Lead Time
5 26 Dec 2021 Unplanned work High High High Project Manager Review all plans and scope; document assumptions; communicate clearly Escalate to project manager; develop mitigation plan for cost/schedule Project manager to meet with project sponsor Open Project Schedule
6 27 Dec 2021 Lack of communication causes issues High High High Project Manager Create proper communication plan and ensure adherence Clarify misunderstandings immediately; seek sponsor support Communication plan in progress In Progress Communication Plan

Risk Monitoring and Control

The risk owner is tasked with:

Change Control Management

As the project is being implemented, a risk may be realized and become issue: a problem or situation that has already happened and requires resolution. There may also be non- conformances: failure to meet specific documented requirements or plans. There may also be new requests from a client to change the scope. All these changes need to be managed strategically to ensure prevention of scope creep and enable project success.

A change management systems is created for the project to ensure systematic change management. This is achieved through the following steps:

  1. Identify proposed changes (this is done by requiring change request submissions for each risk)
  2. List expected effects of proposed change(s) on schedule and budget
  3. Review, evaluate, and approve or disapprove of changes formally
  4. Negotiate and resolve conflicts of change, condition, and cost
  5. Communicate changes to parties affected
  6. Assign responsibility for implementing change
  7. Adjust master schedule and budget
  8. Track all changes that are to be implemented

By defining these various steps:

  1. Inconsequential changes are discouraged by the formal process
  2. Costs of changes are maintained in a log
  3. Integrity of the WBS and performance measures is maintained
  4. Allocation and use of contingency and management reserves are tracked
  5. Responsibility for implementation is clarified
  6. Effect of changes is visible to all parties involved
  7. Implementation of change is monitored
  8. Scope changes will be quickly reflected in baseline and performance measures

Example: Project Change Request

Project Name: Irish/Chinese culture exchange
Project Sponsor: Irish embassy
Request Number: 12
Date: June 6, 2xxx
Originator: Jennifer McDonald
Change Requested By: Chinese culture office

Description of Requested Change

  1. Request river dancers to replace small Irish dance group.
  2. Request one combination dance with river dancers and China ballet group.

Reason for Change River dancers will enhance the stature of the event. The group is well known and loved by Chinese people.

Areas of Impact

Disposition

Priority

Funding Source

Sign-off Approvals

Change Request Tracking

Owner Requested Change Status Report — Open Items

Rc# Description Reference Document Date Rec’d Date Submit Amount Status Comments
51 Sewer work offset — — — –188,129 OPEN Funding from other source
52 Stainless Plates at restroom Shower Valves ASI 56 1/5/2020 3/30/2020 9,308 APPROVED —
53 Waterproofing Options ASI 77 1/13/2020 — 169,386 OPEN —
54 Change Electrical floor box spec change RFI 113 12/5/2020 3/29/2020 2,544 SUBMIT —
55 VE Option for Style and rail doors Door samples 1/14/2020 — –20,000 ROM —
56 Pressure Wash C tower Owner request 3/15/2020 3/30/2020 14,861 SUBMIT —
57 Fire Lite glass in stairs Owner request — — 8,000 QUOTE ROM based on FireLite NT
58 Cyber Café added tele / OFOI equipment ASI 65 1/30/2020 3/29/2020 4,628 APPROVED —
59 Additional Dampers in C wing ASI 68 2/4/2020 3/29/2020 1,085 SUBMIT —
60 Revise Corridor ceilings ASI 72 2/13/2020 3/31/2020 –3,755 SUBMIT —

Legend

Risk vs Issue

Risks are uncertain future event with a positive or negative impact on the project. A realized risk is a risk that has become a reality. If the realized risk can be overcome with the existing mitigation or contingency plan, then the system is working. However, it the realized risk is not resolved, or something happens that we did not expect, we have an issue.

An issue is a problem or situation that has already happened and requires resolution. It may be a nonconformance: Failure to meet specific documented requirements. Or it may be an anomaly: An unexpected observation that needs vetting to determine if it reflects a real problem. In any case, issues are to be tracked and resolved.

Feature Risk Issue
Timing Future Present
Probability Uncertain Certain
Nature Positive or negative Almost always negative
Resolution Mitigation planning Immediate action and resolution

Summary