By the end of this unit, you should be able to:
Before starting to create a preliminary plan in project management software you should have the following information:
To start a project, we need to set up a few items:


Most project management software use a table representation to enter the WBS. Indenting activities will make them a subactivity, while outdenting will remove them from a subactivity structure.
The software does provide a visual representation of the WBS as well.

For each activity in the WBS, we have to define the following properties:

Based on the start date, calendar, durations of the activities, and their relationships, the software automatically creates the schedule. You can see the schedule as a Gannt Chart or as a network diagram.

To add cost information to your plan, you first need to create:
Next, you assign the resources to the activities by determing the number of FTE they spend on the project.
By default, ProjectLibre performs effort-driven scheduling, so assigning resources has an impact on duration. You can change this in the advanced settings for each task.
Now, we can see the resource loading in tabular or graphic form.


With the resources assigned, cost information now shows up on the WBS, as seen in the previous section. Additional columns can be added to review these as well.
When the plan seems reasonable, you can “save baseline”. This will save the planned state as a standard. After baselining, any changes to the plan, including adding information, changes to resources, etc will be tracked and can be compared to the original. In the example below, tracking information has been added and is visible as solid black lines on the bars. The gray lines show the baseline plan. In this case, the duration of task 5 has increased, which has shifted the whole network to the right compared to the original plan.

The example in this section is from the following source, recreated in ProjectLibre: