ProjectManagementOER

Resource Planning Processes

Learning Objectives

By the end of this unit, you should be able to:

Plan Resource Management

This process focuses on creating a description for how resources will be managed by the project (including where resources come from, how they are assigned to the project, who manages them, what their responsibilities are, standard calendar for the project, etc). It has the following elements:

Estimate Activity Resources

The goal of this process is to estimate how many resources are assigned to each activity.

Resource Allocation

Resource allocation focuses on assigning human resource, technical resources (equipment), and other resources (financial, materials, etc) to projects. Resources may be assigned to a single project or multiple, simultaneous projects. Some resources are used up by the project (consumable), while others have operational tasks they need to perform. When a resource is needed is determined by the project network, while the use of resources has cost implications for the project.

Keep in mind that:

After we have assigned the resources to the tasks, and scheduled the project based on the availability of resources, we are ready to create a time-phased budget baseline: a representation of when cash is used by the project. This will allow us to monitor the progress of the project:

Why are resources a limiting factor?

The critical path method assumes that resources are unlimited; however, real projects compete with each other for resources:

  1. If a resource is used but not consumed, a project must wait to use resource
  2. If a resource is consumed during use, projects need to procure additional resource and wait for replacement In either case, one project must wait. As such, resource limitations can delay a project or specific activities in a project.

By considering resources when creating a schedule, we can:

In fact, one can claim that:

Resource Scheduling

To schedule resources:

  1. Create a network diagram
  2. Estimate durations (at this point, you are assuming ideal conditions)
    • Those doing the work must do estimate (and change sequence if necessary and measure actual performance)
  3. Assign required resources to each task (this is done under ideal conditions based on the duration you selected and effort needed for the activity)
    • For outsourced activities, team resources are zero though you may need to consider resources available by your contractor
    • Outsourcing removes your control though so outsourcing the critical path is not recommended
  4. Convert to Gannt chart and add up resources required in each period
  5. Define resources available in each period and compare to your plan
  6. Reschedule activities within float to balance resources required and resources available

Ideally you would like to schedule as if resource is fully dedicated to the task, focuses on one thing at a time. However, in matrix organizations this is not possible.

Resource Allocation Considerations

In selecting who to assign to specific tasks consider:

You may then map the utilization of resources to the activities and the project timeline in the form of a resource usage calendar:

c99cf06aec69535d5f8eccf1ebaa6f20.png

You may also visualize the usage of resources as a resource usage profile over time: 092c540f2552358655433ff1360c16d5.png

Project Constraints and Scheduling

While considering resources, it is important to consider what constraints are driving the decisions within the project:

The project itself will be either:

Example: Time-Constrained vs Resource-Constrained Projects

Looking at the Valley College online registration system, the goal may be for the system to go live before the Fall registration period. The college can add contractors or pay overtime if necessary to keep the deadline, making time fixed and resources flexible. This will be a time-constrained project.

Alternatively, the college may decide to assign a fixed team of 5 staff, and fixed financial resources for the implementation. The team then needs to plan and tell the college when they think they can launch the system. In this situation, the project will be resource-constrained.

Resource Loading and Leveling/Smoothing

Resource loading refers to the amounts of specific resources (capacity, utilization) that are scheduled for use by specific activities or projects at specific time. It is usually presented in the form of a list or table. In most cases, you want a specific resource loading throughout the project (say you want someone to work 40% of their time on your project). Resource availability, needs, etc may fluctuate over time such that resources required and capacity available may not be constant.

After the project plan is developed, the PM confirms the availability of each resource required resource and obtains schedules for each. It is easy to over utilize a human resource, and this may in fact lead to overtime pay (costing the project) or burnout (low performance for the project). Holidays, vacations, sick days can reduce human resource availability. Moreover, not all required facilities and equipment will be available when needed, there may be changes requested to the project and some risk event may delay tasks. Resource allocation should factor in all these possibilities.

The project manager will then review the resource loading of each resource: the work allocated to a resource should match their availability. If this is not the case, then we would need to change the schedule through resource leveling or smoothing:

If none of these approaches work, then there may be a need to change the supply of resources, outsource part of the work or split activities. The same may be true if the project is impacted by disruptions, emergencies, maintenance, personnel issues, or inefficiencies. Most organizations also schedule scarce resources between 85-90% capacity, to keep some capacity for emergencies.

6a8d64280fdba15322280374a6442100.png Source: Project Management Institute. (2022). Process Groups: A Practice Guide. Newtown Square, Pennsylvania: Project Management Institute.

Example: Resource Leveling for a Specialist

Let’s go back to Valley College’s new online registration system project. Integration specialist “Alex” is needed for 3 tasks:

Original plan mistakenly overlaps T1 and T2, requiring Alex at 150% capacity. Resource analysis reveals the overload. The project manager decides to move T2 to start immediately after T1 finishes, using available slack in non‑critical activities. This resource leveling reduces Alex’s allocation to 100%, avoiding burnout and overtime.  It does delay the project finish date by 3 days, which may be acceptable if the project is resource‑constrained rather than strictly time‑constrained.

Resource Smoothing vs Leveling

Consider a residential construction project. If the project is strictly resource-constrained—meaning the organization employs only one licensed electrician, but the schedule dictates simultaneous wiring in two separate wings of the house—the project manager must utilize resource leveling. Because the resource constraint cannot be violated, the schedule must be extended. The electrician completes the first wing before transitioning to the second, which inherently alters the critical path and delays the project’s overall completion date.

Conversely, if the project is strictly time-constrained—meaning the house must be completed before the winter frost sets in—the project manager must utilize resource smoothing. In this scenario, the organization may have sufficient carpenters, but the software indicates a massive, budget-breaking spike in carpentry hours during week three. Because the final deadline cannot shift, the critical path remains locked. The project manager smooths the resource demand by identifying non-critical carpentry tasks (those possessing ample total float, such as constructing custom interior shelving) and delaying them to week four. This flattens the peak resource demand without altering the project finish date.

Resource-Smoothing in Practice

In resource-constrained projects, activities are scheduled using heuristics (rules of thumb) by following the priority rules for resource allocation:

  1. Minimum slack (most urgent)
  2. Smallest (least) duration
  3. Most critical followers
  4. Most successors
  5. Most resources first
  6. Lowest activity identification number

The parallel method is used to apply heuristics: start from the beginning of project time and, when the resources needed exceed the resources available, retains activities first by the priority rules.

Another approach is to use optimization methods in your project management software. These finds the one best solutions by considering various adjustments.

KPIs to consider include:

Keep in mind that this smoothing approach:

Splitting Activities

Splitting is a scheduling technique used to get a better project schedule and/or to increase resource utilization. It involves interrupting the work and sending the resource to another activity for a period of time and then having the resource resume work on the original activity. It can be useful if the work involved does not include large start-up or shut-down costs/time. Splitting is also considered a major reason why projects fail to meet schedule.

Multi project Resource Scheduling Problems

When allocating scarce resources is extended to where several projects being carried out concurrently, the size and complexity of the problem increases. However, the nature of the underlying problem remains the same

  1. Overall schedule slippage: Shared resources causes a ripple effect—delays in one project create delays for other projects
  2. Inefficient resource utilization: Different schedules and requirements by multiple projects create the peaks and valleys in overall resource demands
  3. Resource bottlenecks: Shortages of critical resources required by multiple projects cause delays and schedule extensions

To address these issues:

Goldratt’s Critical Chain

There are several common issues faced when implementing a project:

Goldratt took these issues into account, and applied the theory of constraints to the constrained resource scheduling problem. He assumed that problems encountered when managing projects are strongly related to the need to trade off one project objective for another, and the need to make these trade-offs caused by human decisions and practices. The scenario below describes a common chain of events:

  1. Assuming that activity times are known and that the paths are independent leads to underestimating the actual amount of time needed to complete the project.
  2. Because the time needed to complete the project is underestimated, project team members tend to inflate their time estimates.
  3. Inflated time estimates lead to work filling available time, workers not reporting that a task has been completed early, and the ever-present student syndrome.
  4. An important caveat then becomes that safety time is usually visible to project workers and is often misused.
  5. Misused safety time results in missed deadlines and milestones.
  6. Hidden safety time further complicates the task of prioritizing project activities.
  7. The lack of clear priorities likely results in poor multitasking.
  8. Task durations increase as a result of poor multitasking.
  9. Uneven demand on resources—some overloaded and others under-loaded—may also occur as a result of poor multitasking.
  10. In an effort to utilize all resources fully, more projects will be undertaken to make sure that no resources are underutilized.
  11. Adding more projects further increases poor multitasking.

Goldratt suggested that the key to resolving this cycle is to schedule the start of new projects based on the availability of bottleneck resources. Time buffers should be added between the bottleneck resource and the resources that feed it to reduce risks. Moreover, safety time of individual tasks should be limited and, instead, some fraction of the safety time reduced this way should be added back into the system as safety buffer for the entire project.

The critical chain is the sequence of both precedence- and resource-dependent tasks that prevents a project from being completed in a shorter time, given finite resources. When scheduling using this method, you cut down time estimates by 50%, the 50% you cut is left is allocated to buffers:

Summary

Practice

Bibliography

The following sources were also consulted in creating this resource: