Projects within Organizations

Learning Objectives

By the end of this unit, you should be able to:

Situating the Project in the Organization

Before we jump into assigning resources, we should assess where the project is within the organization, and decide how the project is organized. This will inform where the resources we need will come from.

Project Influences from the Organization

A project is influenced by the organization it happens in. These influences take two forms:

  1. Enterprise environmental factors
    • Internal
      • Organizational culture, structure, and governance
      • Geographic distribution of facilities and resources
      • Infrastructure
      • Information technology software
      • Resource availability
      • Employee capability
    • External
      • Marketplace conditions
      • Social and cultural influences and issues
      • Legal restrictions
      • Commercial databases
      • Academic research
      • Government or industry standards
      • Financial considerations
      • Physical environmental elements
  2. Organizational process assets
    • Processes, Documents and Templates
    • Organizational Knowledge Repository (past projects and know-how)

These influences continuously impact project management in all areas, and as such are inputs to almost all project management processes.

Organizational Culture

Organizational culture is the system of shared norms, beliefs, values, and assumptions that binds people together, thereby creating shared meanings and affecting the behaviour of organization members.

Organizational culture:

Project managers interact with several cultures and subcultures belonging to:

Project managers can get a better picture of the organization’s culture by:

Corporate culture can be characterizes along a continuum of dimensions including:

  1. Member identity: Job-focus vs Organization-focus
  2. Team emphasis: Individual vs Group
  3. Management focus: Task vs People
  4. Unit integration: Independent vs Interdependent
  5. Control: Loose vs Tight
  6. Risk tolerance: Low vs High
  7. Reward criteria: Performance vs Other
  8. Conflict tolerance: Low vs High
  9. Means-ends orientation: Means vs Ends
  10. Open-system focus: Internal vs External

Of particular relevance to the project manager is to understand the following factors for each organization:

Organizational Structures

Projects happen within an organization, and as such are impacted by how the organization is structured. From a project management perspective, organizations can have 3 broad structures which, on order of increasing project management authority, are:

  1. Functional Organization
  2. Matrix Organization
    • Weak Matrix
    • Balanced Matrix
    • Strong Matrix
  3. Projectized Organization or dedicated project teams

Organizations may change their structure to increase success on a project. These types of organizations form a continuum, with activities being organized in a functional way at one end and projectized way at the other.

Criteria Mechanistic/Functional Organic / Projectized
Standardization Highly formalized Low
Specialization High/Narrow Low/Broad
Centralization Centralized Decentralized
Departmentalization Functional Divisional

Organization Continuum

Picking the right structure for the project is impacted by many factors:

Keep in mind that organizational structures are not set in stone: they evolve. Early on, most organization start with a flat structure with minimal or none-existent processes. The goal here is:

If the organization survives this stage, then structures start to emerge with the goal of supporting:

Organizations that survive that stage start having a basic, developing structure with:

Organizations may reach a stage where there need to be an extensive reassessment of their structure:

Functional Organization

In a functional organization, operational activities are separate into functions based on the domain knowledge required or discipline. This is commonly seen in large organizations. Traditional functional departments might include:

In these organizations, projects are either defined within a function, or in the case of cross-functional projects, top management decides to implement the project, and different segments of the project are distributed to appropriate functions. Coordination is maintained through normal management channels, meaning that the functional managers would coordinate with each other to ensure the work is complete. The success of projects within a functional organization depends on functional managers working together and cooperating.

There is no real “project team”, and in many cases there is no project manager assigned. This approach is highly hierarchical/bureaucratic. It is commonly used when one functional area plays a dominant role in completing the project or has a dominant interest in the success of the project.

The benefits of functional organizations are:

However, there are many drawbacks:

  Chief Exec  
Functional Manager Functional Manager Functional Manager
Staff Staff Staff
Staff Staff Staff
Staff Staff Staff

Project coordination happens at functional manager level (italics). Project team members (bold) report to different managers.

Projectized Organizations or Dedicated Teams

Projectized organizations are at the opposite end of the organizational spectrum from functional organizations. Here projects are the dominant form of business; as a result, the entire organization is designed to support project teams. In a projectized organization, operations are minimal and the project manager has great authority over resources and personnel decisions.

Dedicated project teams (be it in a projectized or functional organization) operate as units separate from the rest of the parent organization. A full-time project manager is designated to pull together a core group of specialists who work full time on the project. The project manager recruits necessary personnel from both within and outside the parent company. On the highest end of flexibility, these teams can become self-managed (similar to how university team projects work) where the team has no pre-existing hierarchy and shared leadership. “Projectitis” is referred to as a negative dimension to dedicated project teams.  A we-they attitude can emerge between project team members and the rest of the organization.

The benefits of dedicated project teams are:

The drawbacks include:

  Chief Exec  
Project Manager Project Manager Project Manager
Staff Staff Staff
Staff Staff Staff
Staff Staff Staff

Project management is focused and dedicated (italics) and project team (bold) just reports to the project manager for all aspects.

Matrix Organization

A matrix structure tries to combine the strengths a functional organization provides for operations management with the strengths a projectized organization provides for project management. In this hybrid approach, horizontal project management structure is overlaid on the normal functional hierarchy.

There are usually two chains of command, one along functional lines and the other along project lines. Project participants report simultaneously to both functional and project managers. As a result, there should be a clear understanding of PM and FM roles needed:

The matrix structure provides dual focus between functional/technical expertise and project requirements.The matrix structure is designed to utilize resources optimally. Individuals work on multiple projects as well as being capable of performing normal functional duties. It attempts to achieve greater integration by creating and legitimizing the authority of a project manager.

The benefits of the matrix structure are:

However, the drawbacks include:

    Chief Exec  
  Functional Manager Functional Manager Functional Manager
Project Manager Staff Staff Staff
Project Manager Staff Staff Staff
Project Manager Staff Staff Staff

Staff report to both project manager (project reporting) and functional manager (functional authority).

Overall, a matrix approach is appropriate when there is:

Matrix organizations can have different strengths:

  1. Weak matrix: This form is very similar to a functional approach with the exception that there is a formally designed project manager responsible for coordinating project activities. Functional managers are responsible for managing their segment of the project (including devoting capacity to the project), while the project manager acts as a coordinator who draws the schedules and checklists, collects information on the status of the work, and facilitates project completion.
  2. Balanced matrix: The project manager is responsible for defining what needs to be accomplished, establishing the overall plan for completing the project, integrating the contribution of the different disciplines, setting schedules, and monitoring progress. The functional managers are concerned with how it will be accomplished, assigning personnel and executing their segment of the project according to the standards and schedules set by the project manager.
  3. Strong matrix: Here the project manager controls most aspects of the project, including scope trade-offs, assignment of functional personnel, when and what specialists do and has final say on major project decisions. The functional managers have title over their people and are consulted on a need basis. They essentially act as subcontractors for the project.

Generally speaking, in budget- or time-driven projects we strengthen the matrix, which emphasizes the project as opposed to specific disciplines. In quality-driven project, we weaken the matrix to emphasize the disciplines.

Organizational Structures in Practice

Let’s focus on the case of Valley College implementing a new online registration system.

In a functional organization, the project management may be assigned to this from the IT department. They:

In a Strong matrix organization, the project manager may be still assigned from the IT department.

In a Projectized organization, the university may hire a dedicated project manager for this project.

Which Organizational structure to use

This depends on how important the project is:

Organizational Structure Type Work Groups Arranged By Project Manager’s Authority Project Manager’s Role Resource Availability Who Manages the Project Budget? Project Management Administrative Staff
Organic / Simple Flexible, loosely organized Variable / Low Variable Limited Functional Manager / Mixed Part-time / Minimal
Functional (Centralized) Functions / Departments Little or None Part-time Little or None Functional Manager Part-time
Multidivisional Divisions (replicated functions) Low to Moderate Part-time / Mixed Low to Moderate Division Manager / Mixed Part-time
Matrix – Weak Functions with limited PM influence Limited Part-time Limited Functional Manager Part-time
Matrix – Balanced Functions + Projects equally Low to Moderate Full-time Low to Moderate Mixed Part-time
Matrix – Strong Project-focused with functional support Moderate to High Full-time Moderate to High Project Manager Full-time
Projectized Projects High to Almost Total Full-time High to Almost Total Project Manager Full-time
Project-oriented (Composite / Hybrid) Mixed functional + project Moderate Full-time Moderate Mixed / PM Full-time / Mixed
Virtual Distributed teams / networked Low to Moderate Full-time / Coordinating Limited to Moderate Mixed Part-time / Virtual Support
Hybrid Combination of structures Variable Variable Variable Mixed Variable
PMO (Portfolio/Program/Project Management Office) Centralized PM authority High Full-time High PMO Full-time

Summary of different organizational structures. Adapted from Project Management Institute. (2022). Process Groups: A Practice Guide. Newtown Square, Pennsylvania: Project Management Institute. and PMBOK Guide 5th ed.

Vasconcellos & Hemsley, PMI Proceedings 1981, as adapted by Dinsmore reports these results from a survey of managers on the performance of the various organization structures:

Criteria Projectized Matrix Functional
Achievement of due dates V. good Poor Poor
Technical Qualities Poor Good V. good
Resource Utilization Poor Good V. good
Cost Control V. good Good Poor
Job satisfaction for specialists Poor Good V. good
Job satisfaction for non-specialists V. good Good Poor
Client feedback and control V. good Good Poor
Conflict Low High Low

Summary

Practice

Bibliography

The following sources were also consulted in creating this resource: