By the end of this unit, you should be able to:
Before we jump into assigning resources, we should assess where the project is within the organization, and decide how the project is organized. This will inform where the resources we need will come from.
A project is influenced by the organization it happens in. These influences take two forms:
These influences continuously impact project management in all areas, and as such are inputs to almost all project management processes.
Organizational culture is the system of shared norms, beliefs, values, and assumptions that binds people together, thereby creating shared meanings and affecting the behaviour of organization members.
Organizational culture:
Project managers interact with several cultures and subcultures belonging to:
Project managers can get a better picture of the organization’s culture by:
Corporate culture can be characterizes along a continuum of dimensions including:
Of particular relevance to the project manager is to understand the following factors for each organization:
Projects happen within an organization, and as such are impacted by how the organization is structured. From a project management perspective, organizations can have 3 broad structures which, on order of increasing project management authority, are:
Organizations may change their structure to increase success on a project. These types of organizations form a continuum, with activities being organized in a functional way at one end and projectized way at the other.
| Criteria | Mechanistic/Functional | Organic / Projectized |
|---|---|---|
| Standardization | Highly formalized | Low |
| Specialization | High/Narrow | Low/Broad |
| Centralization | Centralized | Decentralized |
| Departmentalization | Functional | Divisional |
Picking the right structure for the project is impacted by many factors:
Keep in mind that organizational structures are not set in stone: they evolve. Early on, most organization start with a flat structure with minimal or none-existent processes. The goal here is:
If the organization survives this stage, then structures start to emerge with the goal of supporting:
Organizations that survive that stage start having a basic, developing structure with:
Organizations may reach a stage where there need to be an extensive reassessment of their structure:
In a functional organization, operational activities are separate into functions based on the domain knowledge required or discipline. This is commonly seen in large organizations. Traditional functional departments might include:
In these organizations, projects are either defined within a function, or in the case of cross-functional projects, top management decides to implement the project, and different segments of the project are distributed to appropriate functions. Coordination is maintained through normal management channels, meaning that the functional managers would coordinate with each other to ensure the work is complete. The success of projects within a functional organization depends on functional managers working together and cooperating.
There is no real “project team”, and in many cases there is no project manager assigned. This approach is highly hierarchical/bureaucratic. It is commonly used when one functional area plays a dominant role in completing the project or has a dominant interest in the success of the project.
The benefits of functional organizations are:
However, there are many drawbacks:
| Chief Exec | ||
|---|---|---|
| Functional Manager | Functional Manager | Functional Manager |
| Staff | Staff | Staff |
| Staff | Staff | Staff |
| Staff | Staff | Staff |
Project coordination happens at functional manager level (italics). Project team members (bold) report to different managers.
Projectized organizations are at the opposite end of the organizational spectrum from functional organizations. Here projects are the dominant form of business; as a result, the entire organization is designed to support project teams. In a projectized organization, operations are minimal and the project manager has great authority over resources and personnel decisions.
Dedicated project teams (be it in a projectized or functional organization) operate as units separate from the rest of the parent organization. A full-time project manager is designated to pull together a core group of specialists who work full time on the project. The project manager recruits necessary personnel from both within and outside the parent company. On the highest end of flexibility, these teams can become self-managed (similar to how university team projects work) where the team has no pre-existing hierarchy and shared leadership. “Projectitis” is referred to as a negative dimension to dedicated project teams. A we-they attitude can emerge between project team members and the rest of the organization.
The benefits of dedicated project teams are:
The drawbacks include:
| Chief Exec | ||
|---|---|---|
| Project Manager | Project Manager | Project Manager |
| Staff | Staff | Staff |
| Staff | Staff | Staff |
| Staff | Staff | Staff |
Project management is focused and dedicated (italics) and project team (bold) just reports to the project manager for all aspects.
A matrix structure tries to combine the strengths a functional organization provides for operations management with the strengths a projectized organization provides for project management. In this hybrid approach, horizontal project management structure is overlaid on the normal functional hierarchy.
There are usually two chains of command, one along functional lines and the other along project lines. Project participants report simultaneously to both functional and project managers. As a result, there should be a clear understanding of PM and FM roles needed:
The matrix structure provides dual focus between functional/technical expertise and project requirements.The matrix structure is designed to utilize resources optimally. Individuals work on multiple projects as well as being capable of performing normal functional duties. It attempts to achieve greater integration by creating and legitimizing the authority of a project manager.
The benefits of the matrix structure are:
However, the drawbacks include:
| Chief Exec | |||
|---|---|---|---|
| Functional Manager | Functional Manager | Functional Manager | |
| Project Manager | Staff | Staff | Staff |
| Project Manager | Staff | Staff | Staff |
| Project Manager | Staff | Staff | Staff |
Staff report to both project manager (project reporting) and functional manager (functional authority).
Overall, a matrix approach is appropriate when there is:
Matrix organizations can have different strengths:
Generally speaking, in budget- or time-driven projects we strengthen the matrix, which emphasizes the project as opposed to specific disciplines. In quality-driven project, we weaken the matrix to emphasize the disciplines.
Let’s focus on the case of Valley College implementing a new online registration system.
In a functional organization, the project management may be assigned to this from the IT department. They:
In a Strong matrix organization, the project manager may be still assigned from the IT department.
In a Projectized organization, the university may hire a dedicated project manager for this project.
This depends on how important the project is:
| Organizational Structure Type | Work Groups Arranged By | Project Manager’s Authority | Project Manager’s Role | Resource Availability | Who Manages the Project Budget? | Project Management Administrative Staff |
|---|---|---|---|---|---|---|
| Organic / Simple | Flexible, loosely organized | Variable / Low | Variable | Limited | Functional Manager / Mixed | Part-time / Minimal |
| Functional (Centralized) | Functions / Departments | Little or None | Part-time | Little or None | Functional Manager | Part-time |
| Multidivisional | Divisions (replicated functions) | Low to Moderate | Part-time / Mixed | Low to Moderate | Division Manager / Mixed | Part-time |
| Matrix – Weak | Functions with limited PM influence | Limited | Part-time | Limited | Functional Manager | Part-time |
| Matrix – Balanced | Functions + Projects equally | Low to Moderate | Full-time | Low to Moderate | Mixed | Part-time |
| Matrix – Strong | Project-focused with functional support | Moderate to High | Full-time | Moderate to High | Project Manager | Full-time |
| Projectized | Projects | High to Almost Total | Full-time | High to Almost Total | Project Manager | Full-time |
| Project-oriented (Composite / Hybrid) | Mixed functional + project | Moderate | Full-time | Moderate | Mixed / PM | Full-time / Mixed |
| Virtual | Distributed teams / networked | Low to Moderate | Full-time / Coordinating | Limited to Moderate | Mixed | Part-time / Virtual Support |
| Hybrid | Combination of structures | Variable | Variable | Variable | Mixed | Variable |
| PMO (Portfolio/Program/Project Management Office) | Centralized PM authority | High | Full-time | High | PMO | Full-time |
Summary of different organizational structures. Adapted from Project Management Institute. (2022). Process Groups: A Practice Guide. Newtown Square, Pennsylvania: Project Management Institute. and PMBOK Guide 5th ed.
Vasconcellos & Hemsley, PMI Proceedings 1981, as adapted by Dinsmore reports these results from a survey of managers on the performance of the various organization structures:
| Criteria | Projectized | Matrix | Functional |
|---|---|---|---|
| Achievement of due dates | V. good | Poor | Poor |
| Technical Qualities | Poor | Good | V. good |
| Resource Utilization | Poor | Good | V. good |
| Cost Control | V. good | Good | Poor |
| Job satisfaction for specialists | Poor | Good | V. good |
| Job satisfaction for non-specialists | V. good | Good | Poor |
| Client feedback and control | V. good | Good | Poor |
| Conflict | Low | High | Low |